πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Angels Creek

Angels Creek is a 31.7 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0508
Grid region
ERCOT (Texas)
Developer
Angels Creek LLC
Connection point (POI)
5888 Bruni 69kV
Technology
Battery: 31.7 MW
Total requested
31.7 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
3 June 2020
Proposed online date
June 2026
Withdrawn
August 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem