πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

XE RHODA Solar

XE RHODA Solar is a 33.7 MW solar request withdrawn in the ERCOT interconnection queue, in Milam County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2020 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0358
Grid region
ERCOT (Texas)
Developer
Milam 2 Solar
Connection point (POI)
Tap 138kV 32 Robertson - 64 Milano
Location
Milam County, Texas
Technology
Solar: 33.7 MW
Total requested
33.7 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
9 July 2020
Proposed online date
August 2024
Withdrawn
October 2023

Location

Marker shows the centre of Milam County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Milam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem