Withdrawn queue requests in the USA — page 214

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 214 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 534, Butler County
Solar
115 MWWithdrawn / abandoned Butler, KYSoutheast Mar 2023target 2026
Ruby Storage Project
Battery storage · Hanwha Q CELLS USA
115 MWWithdrawn / abandoned Ontario, NYNYISO Sep 2021
Solar project 20230828006, Calhoun County
Solar
115 MWWithdrawn / abandoned Calhoun, SCSoutheast target 2026
Solar project J2112, Hardin County
Solar
115 MWWithdrawn / abandoned Hardin, TXMISO Dec 2021target 2024
Geothermal project C1-05, Millard County
Geothermal
115 MWWithdrawn / abandoned Millard, UTWest Apr 2021target 2026
Verona Solar II
Solar · Verona Solar II LLC
115 MWWithdrawn / abandoned Oneida, NYNYISO Aug 2024
Onshore wind project 74, Box Elder County
Onshore wind
115 MWWithdrawn / abandoned Box Elder, UTWest Apr 2006target 2007
Battery storage project AG2-225, Anne Arundel County
Battery storage
115 MWWithdrawn / abandoned Anne Arundel, MDPJM Mar 2021target 2022
Sun Valley 2
Solar · Sun Valley Solar LLC
115 MWWithdrawn / abandoned Hill, TXERCOT Mar 2019target 2021
Solar project AG2-467, Logan County
Solar · Invenergy Solar Project Development LLC
115 MWWithdrawn / abandoned Logan, ILPJM Mar 2021target 2025
Solar project AH1-484, Henry County
Solar
115 MWWithdrawn / abandoned Henry, INPJM Sep 2021target 2023
Battery Storage
Battery storage
115 MWWithdrawn / abandoned Norfolk, MAISO-NE Nov 2023target 2029
Solar + storage project AH1-388, Mecklenburg County
Solar + storage
115 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2021target 2024
Gas project AH1-741, Prince William County
Gas · Virginia Electric and Power Company
115 MWWithdrawn / abandoned Prince William, VAPJM target 2030
Battery storage project J2365, Portage County
Battery storage
115 MWWithdrawn / abandoned Portage, WIMISO Sep 2022target 2030
Solar + storage project 612, Elmore County
Solar + storage
115 MWWithdrawn / abandoned Elmore, IDWest Jul 2021
OYA Fort Plain Solar
Solar · OYA Solar CDG LLC
115 MWWithdrawn / abandoned Montgomery, NYNYISO Mar 2021
Solar project IC-709, Jefferson County
Solar
115 MWWithdrawn / abandoned Jefferson, GASoutheast May 2018
Solar project J1972, Des Moines County
Solar
115 MWWithdrawn / abandoned Des Moines, IAMISO Aug 2021target 2025
NY Amsterdam 152 Persons Rd Storage
Battery storage · Bluewave Storage Origination LLC
115 MWWithdrawn / abandoned Montgomery, NYNYISO Oct 2022
Battery Storage
Battery storage
115 MWWithdrawn / abandoned Windsor, VTISO-NE Apr 2024target 2028
Savanna Prairie Storage
Battery storage · Savanna Prairie Storage, LLC
114 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Solar project J2358, Madison County
Solar
114 MWWithdrawn / abandoned Madison, MSMISO Sep 2022target 2024
Blue Summit W 2
Onshore wind · Nextera
114 MWWithdrawn / abandoned ERCOT Feb 2013target 2018
Meadow Ridge Solar And Battery
Solar + storage
114 MWWithdrawn / abandoned Shasta, CACAISO Apr 2021target 2034
Solar project 20180209001, Barnwell County
Solar
113 MWWithdrawn / abandoned Barnwell, SCSoutheast target 2020
Solar project 20151028001, Orangeburg County
Solar · Southern Grove Solar
113 MWWithdrawn / abandoned Orangeburg, SCSoutheast target 2021
Gas project 153, Horry County
Gas
113 MWWithdrawn / abandoned Horry, SCSoutheast Jan 2021
Sequan
Battery storage
113 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Onshore wind project GI-0515, Dewey County
Onshore wind · Citizens Enterprises
113 MWWithdrawn / abandoned Dewey, SDWest Nov 2005target 2012
Keechi Creek Wind Farm
Onshore wind · Texas Land Partners
113 MWWithdrawn / abandoned ERCOT Jun 2007target 2050
Solar project J4035, Greene County
Solar
113 MWWithdrawn / abandoned Greene, ARMISO Jun 2025target 2029
Solar + Battery Storage
Solar + storage
113 MWWithdrawn / abandoned Coos, NHISO-NE May 2021target 2025
Gas project AB2-074, Snyder County
Gas
113 MWWithdrawn / abandoned Snyder, PAPJM Apr 2016target 2019
Gas project 322, Silver Bow County
Gas
113 MWWithdrawn / abandoned Silver Bow, MTWest Jun 2017target 2019
Rustler Solar
Solar · Cypress Creek Renewables
113 MWWithdrawn / abandoned ERCOT Sep 2017target 2020
Solar project GEN-2014-070, Lea County
Solar
113 MWWithdrawn / abandoned Lea, NMSPP Sep 2014target 2016
Solar project IC-651, Jenkins County
Solar
113 MWWithdrawn / abandoned Jenkins, GASoutheast Aug 2017
SSE phase 1
Onshore wind · Spinning Star Energy LLC
113 MWWithdrawn / abandoned ERCOT Jul 2011target 2050
Wind
Onshore wind
113 MWWithdrawn / abandoned Franklin, MEISO-NE Nov 2015target 2019
Sodis Storage
Battery storage
112 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2021target 2024
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Exchequer
Hydro
112 MWWithdrawn / abandoned Mariposa, CACAISO May 2017target 2019
FitzPatrick Nuclear Uprate
Nuclear · FitzPatrick Nuclear Station
112 MWWithdrawn / abandoned Oswego, NYNYISO May 2009
Solar project AF2-188, White County
Solar
112 MWWithdrawn / abandoned White, INPJM Mar 2020target 2023
SSE phase 1
Onshore wind · Spinning Star Energy LLC
112 MWWithdrawn / abandoned ERCOT Dec 2012target 2013
Solar project GEN-2022-197, Swisher County
Solar
112 MWWithdrawn / abandoned Swisher, TXSPP Feb 2023target 2027
Gas project J317, Marquette County
Gas
112 MWWithdrawn / abandoned Marquette, MIMISO Nov 2013
Green Valley Gas
Gas · Denton Municipal Electric
112 MWWithdrawn / abandoned ERCOT Nov 2015target 2017
Page 214 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)