United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOOYA Fort Plain Solar
OYA Fort Plain Solar is a 115 MW solar request withdrawn in the NYISO interconnection queue, in Montgomery County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedJul 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1154
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- OYA Solar CDG LLC
- Connection point (POI)
- Clinton Road substation 115 kV
- Location
- Montgomery County, New York
- Technology
- Solar: 115 MW
- Total requested
- 115 MW
- Queue status
- Withdrawn
- Entered queue
- 29 March 2021
- Withdrawn
- July 2021
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Mill Point SolarSolar + storage Β· 250 MW Β· in study
- Kce NY 2Battery storage Β· 200 MW Β· in study
- Flat Creek SolarSolar Β· 200 MW Β· in study
- Amsterdam SolarSolar Β· 150 MW Β· in study
- Flat Creek SolarSolar Β· 100 MW Β· in study
- Mill Point Solar IISolar + storage Β· 100 MW Β· in study
- Mohawk SolarSolar Β· 90.5 MW Β· in study
- High River SolarSolar Β· 90.0 MW Β· built
- High River SolarSolar Β· 90.0 MW Β· built
- PattersonvilleSolar Β· 20.0 MW Β· built
- Grissom SolarSolar Β· 20.0 MW Β· built
- Regan SolarSolar Β· 20.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem