๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2023 requests) โ€” page 21

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests ยท page 21 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2022-225, Muskogee County
Battery storage
200 MWWithdrawn / abandoned Muskogee, OKSPP Feb 2023target 2028
Solar project GEN-2022-124, Scott County
Solar
200 MWWithdrawn / abandoned Scott, KSSPP Feb 2023target 2027
Battery storage project GEN-2022-129, Osage County
Battery storage
200 MWWithdrawn / abandoned Osage, OKSPP Feb 2023target 2027
Van Oker
Battery storage
200 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Solar project GEN-2022-181, Tillman County
Solar
200 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
BPP NY Somerset BESS I
Battery storage ยท Bear Peak Power
200 MWWithdrawn / abandoned Niagara, NYNYISO Sep 2023
Solar + storage project GEN-2023-098, Perkins County
Solar + storage
200 MWWithdrawn / abandoned Perkins, SDSPP Oct 2023target 2027
Canela Energy Storage
Battery storage
200 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Solar project IC-1193, Hancock County
Solar
200 MWWithdrawn / abandoned Hancock, GASoutheast Oct 2023target 2028
Onshore wind project GEN-2023-217, Knox County
Onshore wind
200 MWWithdrawn / abandoned Knox, NESPP Oct 2023target 2026
Battery storage project GEN-2022-163, Canadian County
Battery storage
200 MWWithdrawn / abandoned Canadian, OKSPP Feb 2023target 2026
Onshore wind project GEN-2023-124, Ochiltree County
Onshore wind
200 MWWithdrawn / abandoned Ochiltree, TXSPP Oct 2023target 2030
Egc BESS II
Battery storage ยท Jupiter Power LLC
200 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2023
Solar + storage project C3-060, Iron County
Solar + storage
200 MWWithdrawn / abandoned Iron, UTWest May 2023target 2026
Solar project GEN-2022-234, Rogers County
Solar
200 MWWithdrawn / abandoned Rogers, OKSPP Feb 2023target 2028
Onshore wind project GEN-2023-118, Pratt County
Onshore wind
200 MWWithdrawn / abandoned Pratt, KSSPP Oct 2023target 2030
Onshore wind project G0991, Curry County
Onshore wind
200 MWWithdrawn / abandoned Curry, ORWest Nov 2023target 2028
Onshore wind project 537, Gibson County
Onshore wind
200 MWWithdrawn / abandoned Gibson, TNSoutheast Mar 2023target 2024
Solar project GEN-2023-111, Pratt County
Solar
200 MWWithdrawn / abandoned Pratt, KSSPP Oct 2023target 2030
Solar project 2023-G7
Solar
200 MWWithdrawn / abandoned West Jul 2023target 2026
Onshore wind project Company PL, Pershing County
Onshore wind
200 MWWithdrawn / abandoned Pershing, NVWest Mar 2023target 2025
Battery storage project C3-173, Jefferson County
Battery storage
200 MWWithdrawn / abandoned Jefferson, IDWest May 2023target 2027
Solar project GEN-2023-032, Lafayette County
Solar
200 MWWithdrawn / abandoned Lafayette, MOSPP Oct 2023target 2028
Solar + storage project 531, Mcnairy County
Solar + storage
200 MWWithdrawn / abandoned Mcnairy, TNSoutheast Mar 2023
Battery storage project GEN-2023-189, Lancaster County
Battery storage
200 MWWithdrawn / abandoned Lancaster, NESPP Oct 2023target 2030
Battery storage project SP110, Navajo County
Battery storage
200 MWWithdrawn / abandoned Navajo, AZWest Dec 2023target 2026
Solar project GEN-2022-243, Foard County
Solar
200 MWWithdrawn / abandoned Foard, TXSPP Mar 2023target 2027
Sullivan County Solar & BESS
Solar + storage ยท RWE Solar Development
200 MWWithdrawn / abandoned Sullivan, NYNYISO Jan 2023
Solar + storage project G1046, Lane County
Solar + storage
200 MWWithdrawn / abandoned Lane, ORWest Nov 2023target 2026
Solar + storage project IC-1169, Lowndes County
Solar + storage
200 MWWithdrawn / abandoned Lowndes, ALSoutheast Aug 2023target 2027
Onshore wind project GEN-2022-202, Stevens County
Onshore wind
200 MWWithdrawn / abandoned Stevens, KSSPP Feb 2023target 2027
Solar project GEN-2022-203, Gray County
Solar
200 MWWithdrawn / abandoned Gray, KSSPP Feb 2023target 2029
Solar + storage project Company QD, White Pine County
Solar + storage
200 MWWithdrawn / abandoned White Pine, NVWest Apr 2023target 2026
Solar project IC-1191, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, GASoutheast Oct 2023target 2028
Onshore wind project 23-220, Washington County
Onshore wind
200 MWWithdrawn / abandoned Washington, ORWest Mar 2023target 2028
BPP NY Lansing BESS I
Battery storage ยท Bear Peak Power LLC
200 MWWithdrawn / abandoned Tompkins, NYNYISO Jul 2023
Solar project GEN-2022-123, Scott County
Solar
200 MWWithdrawn / abandoned Scott, KSSPP Feb 20232025
Onshore wind project C3-192, Umatilla County
Onshore wind
200 MWWithdrawn / abandoned Umatilla, ORWest May 2023target 2028
Solar project GEN-2023-087, Cass County
Solar
200 MWWithdrawn / abandoned Cass, MOSPP Oct 2023target 2030
Solar + storage project IC-1141, Lamar County
Solar + storage
200 MWWithdrawn / abandoned Lamar, MSSoutheast May 2023target 2027
Battery storage project GEN-2023-103, Rogers County
Battery storage
200 MWWithdrawn / abandoned Rogers, OKSPP Oct 2023target 2027
Solar project GEN-2023-184, Eddy County
Solar
200 MWWithdrawn / abandoned Eddy, NMSPP Oct 2023target 2030
Battery storage project GEN-2022-165, Swisher County
Battery storage
200 MWWithdrawn / abandoned Swisher, TXSPP Feb 2023target 2026
Solar project IC-1194, Hart County
Solar
200 MWWithdrawn / abandoned Hart, GASoutheast Oct 2023target 2028
Battery storage project C3-051, Franklin County
Battery storage ยท PacifiCorp
200 MWWithdrawn / abandoned Franklin, IDWest May 2023target 2030
Solar + storage project GEN-2023-156, Jefferson County
Solar + storage
200 MWWithdrawn / abandoned Jefferson, OKSPP Oct 2023target 2028
Onshore wind project GEN-2022-190, Kiowa County
Onshore wind
200 MWWithdrawn / abandoned Kiowa, KSSPP Feb 2023target 2027
Nine Mile Wind Energy
Onshore wind ยท Terra-Gen Development Company, LLC
200 MWWithdrawn / abandoned Allegany, NYNYISO May 2023
Solar + storage project C3-163, Crook County
Solar + storage
200 MWWithdrawn / abandoned Crook, ORWest May 2023target 2027
Solar + storage project C3-078, Morrow County
Solar + storage ยท PacifiCorp
200 MWWithdrawn / abandoned Morrow, ORWest May 2023target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)