United States βΊ Grid βΊ Interconnection queues βΊ Oregon
ONSHORE WIND Β· WESTOnshore wind project G0991, Curry County
Onshore wind project G0991, Curry County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Curry County, Oregon.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G0991
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Fairview-Rouge No 1 230 kV line
- Location
- Curry County, Oregon
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 6 November 2023
- Proposed online date
- September 2028
Location
Marker shows the centre of Curry County; the queue data does not give exact sites.
Other requests in Curry County
- Onshore wind project G0972, Curry CountyOnshore wind Β· 300 MW Β· in study
- Battery storage project G0724, Curry CountyBattery storage Β· 280 MW Β· in study
- Onshore wind project G0997, Curry CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G0990, Curry CountyOnshore wind Β· 200 MW Β· withdrawn
- Clipper WindPowerOnshore wind Β· 53.0 MW Β· withdrawn
- JP Saylor and AssociatesOnshore wind Β· 25.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem