πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

ONSHORE WIND Β· WEST

Onshore wind project C3-192, Umatilla County

Onshore wind project C3-192, Umatilla County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Umatilla County, Oregon, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C3-192
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Capstone substation
Location
Umatilla County, Oregon
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 May 2023
Proposed online date
May 2028

Location

Marker shows the centre of Umatilla County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Umatilla County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem