🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Missouri

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Missouri — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8520.6 GW
Active in queue29.7 GW124 requests
Agreement signed7,888 MW34 requests
Withdrawn25251.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

85 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2024-167, Ray County
Battery storage
199 MWIn study Ray, MOSPP Mar 2025target 2030
Battery storage project GEN-2024-181, Greene County
Battery storage
199 MWIn study Greene, MOSPP Mar 2025target 2029
Solar project J1948, Marion County
Solar
195 MWIn study Marion, MOMISO Mar 2022target 2024
Solar project GEN-2024-055, Vernon County
Solar
175 MWIn study Vernon, MOSPP Oct 2024target 2029
Solar project J2288, Ralls County
Solar
175 MWIn study Ralls, MOMISO Jan 2025target 2025
Battery storage project GEN-2024-084, Lawrence County
Battery storage
167 MWIn study Lawrence, MOSPP Oct 2024target 2028
Solar project J3442, Scott County
Solar
156 MWIn study Scott, MOMISO Apr 2024target 2028
Battery storage project J3505, Bollinger County
Battery storage
150 MWIn study Bollinger, MOMISO Apr 2024target 2028
Solar + storage project J2142, Adair County
Solar + storage
150 MWIn study Adair, MOMISO Nov 2021target 2024
Battery storage project GEN-2023-170, Chariton County
Battery storage
150 MWIn study Chariton, MOSPP Oct 2023target 2028
Battery storage project GEN-2023-171, Jackson County
Battery storage
150 MWIn study Jackson, MOSPP Oct 2023target 2028
Solar project J2155, New Madrid County
Solar
150 MWIn study New Madrid, MOMISO Mar 2022target 2024
Gas project GEN-2024-088, Greene County
Gas
145 MWIn study Greene, MOSPP Oct 2024target 2027
Solar + storage project J3229, Maries County
Solar + storage
140 MWIn study Maries, MOMISO Sep 2022target 2026
Solar + storage project J2593, Gasconade County
Solar + storage
140 MWIn study Gasconade, MOMISO Sep 2022target 2026
Solar project GEN-2024-054, Cooper County
Solar
120 MWIn study Cooper, MOSPP Oct 2024target 2029
Solar + storage project J2382, Randolph County
Solar + storage
115 MWIn study Randolph, MOMISO Sep 2022target 2026
Battery storage project GEN-2024-091, Jasper County
Battery storage
100 MWIn study Jasper, MOSPP Oct 2024target 2028
Battery storage project J3736, Osage County
Battery storage
100 MWIn study Osage, MOMISO Apr 2024target 2027
Solar project J2179, Montgomery County
Solar
100 MWIn study Montgomery, MOMISO Aug 2021target 2024
Battery storage project GEN-2022-102, Clay County
Battery storage
100 MWIn study Clay, MOSPP Jan 2023target 2027
Battery storage project GEN-2024-375, Saline County
Battery storage
100 MWIn study Saline, MOSPP Mar 2025target 2029
Battery storage project GEN-2023-061, Jasper County
Battery storage
100 MWIn study Jasper, MOSPP Oct 2023target 2029
Battery storage project GEN-2024-090, Clay County
Battery storage
100 MWIn study Clay, MOSPP Oct 2024target 2028
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4
Other
98.8 MWIn study St. Louis, MOMISO Dec 2024target 2025
Solar + storage project GEN-2021-077, Pettis County
Solar + storage
95.0 MWIn study Pettis, MOSPP Apr 2021target 2027
Solar + storage project GEN-2022-100, Cooper County
Solar + storage
80.0 MWIn study Cooper, MOSPP Mar 2023target 2028
Solar project GI-127, Ralls County
Solar
80.0 MWIn study Ralls, MOSoutheast May 2025target 2028
Other project GEN-2025-SR18, Jackson County
Other
50.0 MWIn study Jackson, MOSPP Jun 2025target 2029
Coal project GI-48, Randolph County
Coal
33.0 MWIn study Randolph, MOSoutheast Oct 2012target 2012
Coal project GI-43, Randolph County
Coal
28.2 MWIn study Randolph, MOSoutheast Nov 2009target 2012
Coal project GI-40, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Coal project GI-39, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Coal project GI-41, Randolph County
Coal
17.0 MWIn study Randolph, MOSoutheast Oct 2009target 2012
Coal project GI-42, Randolph County
Coal
1.7 MWIn study Randolph, MOSoutheast Nov 2009target 2010
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)