Solar + storage project GEN-2022-100, Cooper County

Solar + storage project GEN-2022-100, Cooper County is a 80.0 MW solar + storage request in interconnection study in the SPP interconnection queue, in Cooper County, Missouri, connecting to KCPL.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-100
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Overton - Sedalia East 161 kV Substation
Location
Cooper County, Missouri
Technology
Solar: 80.0 MW · Battery
Total requested
80.0 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
24 March 2023
Proposed online date
March 2028

Location

Marker shows the centre of Cooper County; the queue data does not give exact sites.