United States › Grid › Interconnection queues › Kansas

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Kansas — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown38780.4 GW
Active in queue32.6 GW140 requests
Agreement signed9,162 MW47 requests
Withdrawn38780.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

387 requests · page 2 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-209, Mcpherson County
Solar
300 MWWithdrawn / abandoned Mcpherson, KSSPP Nov 2017target 2026
Solar + storage project GEN-2022-207, Finney County
Solar + storage
300 MWWithdrawn / abandoned Finney, KSSPP Mar 2023target 2027
Onshore wind project GEN-2008-060, Edwards County
Onshore wind
300 MWWithdrawn / abandoned Edwards, KSSPP Jun 2008target 2010
Onshore wind project GEN-2004-010, Cowley County
Onshore wind
300 MWWithdrawn / abandoned Cowley, KSSPP Apr 2004target 2006
Onshore wind project GEN-2008-074, Barber County
Onshore wind
300 MWWithdrawn / abandoned Barber, KSSPP Jul 2008target 2010
Onshore wind project GEN-2018-047, Ellsworth County
Onshore wind
300 MWWithdrawn / abandoned Ellsworth, KSSPP May 2018target 2021
Onshore wind project GEN-2011-002, Cowley County
Onshore wind
300 MWWithdrawn / abandoned Cowley, KSSPP Jan 2011target 2012
Onshore wind project GEN-2008-026, Thomas County
Onshore wind
300 MWWithdrawn / abandoned Thomas, KSSPP Apr 2008target 2009
Solar project GEN-2023-200, Elk County
Solar
300 MWWithdrawn / abandoned Elk, KSSPP Oct 2023target 2028
Battery storage project GEN-2023-026, Anderson County
Battery storage
300 MWWithdrawn / abandoned Anderson, KSSPP Oct 2023target 2027
Onshore wind project GEN-2008-073, Barber County
Onshore wind
300 MWWithdrawn / abandoned Barber, KSSPP Jul 2008target 2010
Solar project GEN-2017-211, Mcpherson County
Solar
300 MWWithdrawn / abandoned Mcpherson, KSSPP Nov 2017target 2021
Onshore wind project GEN-2008-055, Smith County
Onshore wind
300 MWWithdrawn / abandoned Smith, KSSPP Jun 2008target 2011
Solar project GEN-2017-206, Mcpherson County
Solar
300 MWWithdrawn / abandoned Mcpherson, KSSPP Nov 2017target 2021
Onshore wind project GEN-2008-075, Barber County
Onshore wind
300 MWWithdrawn / abandoned Barber, KSSPP Jul 2008target 2011
Onshore wind project GEN-2008-087, Ford County
Onshore wind
300 MWWithdrawn / abandoned Ford, KSSPP Aug 2008target 2012
Solar + storage project GEN-2023-052, Butler County
Solar + storage
300 MWWithdrawn / abandoned Butler, KSSPP Oct 2023target 2028
Onshore wind project GEN-2021-045, Sherman County
Onshore wind
300 MWWithdrawn / abandoned Sherman, KSSPP Apr 2021target 2026
Onshore wind project GEN-2011-017, Hodgeman County
Onshore wind
299 MWWithdrawn / abandoned Hodgeman, KSSPP Mar 20112018
Onshore wind project GEN-2011-023, Ford County
Onshore wind
299 MWWithdrawn / abandoned Ford, KSSPP Mar 2011target 2012
Onshore wind project GI-TC-2024-27, Sherman County
Onshore wind
298 MWWithdrawn / abandoned Sherman, KSWest May 2023target 2028
Onshore wind project GEN-2020-070, Osborne County
Onshore wind
255 MWWithdrawn / abandoned Osborne, KSSPP Apr 20202024
Onshore wind project GEN-2016-157, Allen County
Onshore wind
252 MWWithdrawn / abandoned Allen, KSSPP Nov 20162025
Onshore wind project GEN-2016-158, Allen County
Onshore wind
252 MWWithdrawn / abandoned Allen, KSSPP Nov 20162025
Onshore wind project GEN-2017-147, Johnson County
Onshore wind
252 MWWithdrawn / abandoned Johnson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2016-162, Marion County
Onshore wind
252 MWWithdrawn / abandoned Marion, KSSPP Nov 20162024
Solar project GEN-2018-058, Leavenworth County
Solar
252 MWWithdrawn / abandoned Leavenworth, KSSPP May 20182024
Solar project GEN-2018-059, Leavenworth County
Solar
252 MWWithdrawn / abandoned Leavenworth, KSSPP May 20182024
Onshore wind project GEN-2017-126, Jackson County
Onshore wind
252 MWWithdrawn / abandoned Jackson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2017-125, Osage County
Onshore wind
252 MWWithdrawn / abandoned Osage, KSSPP Nov 2017target 2027
Onshore wind project GEN-2017-124, Jackson County
Onshore wind
252 MWWithdrawn / abandoned Jackson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2020-071, Osage County
Onshore wind
252 MWWithdrawn / abandoned Osage, KSSPP Apr 20202024
Onshore wind project GEN-2017-127, Osage County
Onshore wind
252 MWWithdrawn / abandoned Osage, KSSPP Nov 2017target 2020
Onshore wind project GEN-2016-163, Harvey County
Onshore wind
252 MWWithdrawn / abandoned Harvey, KSSPP Nov 20162024
Onshore wind project GEN-2020-052, Labette County
Onshore wind
251 MWWithdrawn / abandoned Labette, KSSPP Apr 20202025
Onshore wind project GEN-2023-047, Scott County
Onshore wind
250 MWWithdrawn / abandoned Scott, KSSPP Oct 2023target 2030
Onshore wind project GEN-2024-196, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2025target 2028
Onshore wind project GEN-2023-094, Morton County
Onshore wind
250 MWWithdrawn / abandoned Morton, KSSPP Oct 2023target 2028
Onshore wind project GEN-2022-205, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2023target 2027
Battery storage project GEN-2023-073, Butler County
Battery storage
250 MWWithdrawn / abandoned Butler, KSSPP Oct 2023target 2027
Solar project GEN-2018-126, Johnson County
Solar
250 MWWithdrawn / abandoned Johnson, KSSPP Nov 2018target 2021
Onshore wind project GEN-2023-046, Scott County
Onshore wind
250 MWWithdrawn / abandoned Scott, KSSPP Oct 2023target 2030
Onshore wind project GEN-2023-045, Scott County
Onshore wind
250 MWWithdrawn / abandoned Scott, KSSPP Oct 2023target 2030
Onshore wind project GEN-2022-095, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Onshore wind project GEN-2023-090, Finney County
Onshore wind
250 MWWithdrawn / abandoned Finney, KSSPP Oct 2023target 2028
Onshore wind project GEN-2023-048, Scott County
Onshore wind
250 MWWithdrawn / abandoned Scott, KSSPP Oct 2023target 2030
Onshore wind project GEN-2023-140, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Oct 2023target 2028
Onshore wind project GEN-2022-204, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2023target 2027
Onshore wind project GEN-2024-195, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2025target 2028
Onshore wind project GEN-2023-039, Stanton County
Onshore wind
250 MWWithdrawn / abandoned Stanton, KSSPP Oct 2023target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)