United States βΊ Grid βΊ Interconnection queues βΊ Kansas
SOLAR Β· SPPSolar project GEN-2018-059, Leavenworth County
Solar project GEN-2018-059, Leavenworth County is a 252 MW solar request withdrawn in the SPP interconnection queue, in Leavenworth County, Kansas, connecting to WERE.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedApr 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2024 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2018-059
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WERE
- Connection point (POI)
- Stranger Creek 345kV
- Location
- Leavenworth County, Kansas
- Technology
- Solar: 252 MW
- Total requested
- 252 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 May 2018
- Proposed online date
- December 2024
- Came online
- December 2024
- Withdrawn
- April 2023
Location
Marker shows the centre of Leavenworth County; the queue data does not give exact sites.
Other requests in Leavenworth County
- Gas project GEN-2024-253, Leavenworth CountyGas Β· 300 MW Β· in study
- Battery storage project GEN-2024-339, Leavenworth CountyBattery storage Β· 300 MW Β· in study
- Battery storage project GEN-2024-121, Leavenworth CountyBattery storage Β· 199 MW Β· in study
- Gas project GEN-2001-010, Leavenworth CountyGas Β· 640 MW Β· withdrawn
- Gas project GEN-2001-009, Leavenworth CountyGas Β· 640 MW Β· withdrawn
- Solar project GEN-2018-058, Leavenworth CountySolar Β· 252 MW Β· withdrawn
- Onshore wind project GEN-2017-123, Leavenworth CountyOnshore wind Β· 180 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem