Onshore wind project GEN-2011-023, Ford County

Onshore wind project GEN-2011-023, Ford County is a 299 MW onshore wind request withdrawn in the SPP interconnection queue, in Ford County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedSep 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2011-023
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Clark County 345kV
Location
Ford County, Kansas
Technology
Wind: 299 MW
Total requested
299 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2012
Withdrawn
September 2013

Location

Marker shows the centre of Ford County; the queue data does not give exact sites.