Interconnection queue in SPP (Southwest Power Pool) (2025 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26871.3 GW
Active in queue71.3 GW268 requests
Agreement signed0.0 MW0 requests
Withdrawn9926.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

268 requests Β· page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GEN-2024-280, Andrews County
Solar + storage
350 MWIn study Andrews, TXSPP Mar 2025target 2029
Solar project GEN-2024-338, Johnston County
Solar
350 MWIn study Johnston, OKSPP Mar 2025target 2030
Gas project GEN-2024-211, Cass County
Gas
303 MWIn study Cass, NESPP Mar 2025target 2035
Gas project GEN-2024-212, Cass County
Gas
303 MWIn study Cass, NESPP Mar 2025target 2035
Solar project GEN-2024-316, Atoka County
Solar
300 MWIn study Atoka, OKSPP Mar 2025target 2030
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Gas project GEN-2024-254, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Solar project GEN-2024-099, Castro County
Solar
300 MWIn study Castro, TXSPP Mar 2025target 2031
Solar + storage project GEN-2024-113, Sequoyah County
Solar + storage
300 MWIn study Sequoyah, OKSPP Mar 2025target 2028
Onshore wind project GEN-2024-240, Nowata County
Onshore wind
300 MWIn study Nowata, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-215, Cloud County
Solar + storage
300 MWIn study Cloud, KSSPP Mar 2025target 2029
Solar project GEN-2024-226, Hempstead County
Solar
300 MWIn study Hempstead, ARSPP Mar 2025target 2030
Battery storage project GEN-2024-230, Wilbarger County
Battery storage
300 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Gas project GEN-2024-253, Leavenworth County
Gas
300 MWIn study Leavenworth, KSSPP Mar 2025target 2027
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Solar + storage project GEN-2024-336, Yoakum County
Solar + storage
300 MWIn study Yoakum, TXSPP Mar 2025target 2029
Gas project GEN-2024-255, Oklahoma County
Gas
300 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Solar + storage project GEN-2024-364, Randall County
Solar + storage
300 MWIn study Randall, TXSPP Mar 2025target 2028
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Solar project GEN-2024-317, Cottle County
Solar
300 MWIn study Cottle, TXSPP Mar 2025target 2030
Onshore wind project GEN-2024-144, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar project GEN-2024-159, Roosevelt County
Solar
300 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-331, Dunn County
Battery storage
300 MWIn study Dunn, NDSPP Mar 2025target 2028
Gas project GEN-2024-252, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Onshore wind project GEN-2025-GR6, Dimmit County
Onshore wind
300 MWIn study Dimmit, TXSPP Nov 2025
Battery storage project GEN-2024-170, Cass County
Battery storage
280 MWIn study Cass, MOSPP Mar 2025target 2028
Solar + storage project GEN-2024-166, Sedgwick County
Solar + storage
275 MWIn study Sedgwick, KSSPP Mar 2025target 2030
Wind + storage project GEN-2024-278, Lea County
Wind + storage
264 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2025-SR28, Beaver County
Battery storage
263 MWIn study Beaver, OKSPP Aug 2025target 2027
Solar + storage project ERAS-2025-018, Roosevelt County
Solar + storage
256 MWIn study Roosevelt, NMSPP Oct 2025target 2030
Battery storage project GEN-2024-171, Tulsa County
Battery storage
250 MWIn study Tulsa, OKSPP Mar 2025target 2028
Solar project GEN-2024-140, Douglas County
Solar
250 MWIn study Douglas, NESPP Mar 2025target 2033
Solar project GEN-2024-232, Houston County
Solar
250 MWIn study Houston, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-242, Carter County
Battery storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-337, Carter County
Solar + storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Onshore wind project GEN-2024-291, Pittsburg County
Onshore wind
250 MWIn study Pittsburg, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-367, Comanche County
Battery storage
250 MWIn study Comanche, OKSPP Mar 2025target 2028
Onshore wind project GEN-2024-135, Woods County
Onshore wind
250 MWIn study Woods, OKSPP Mar 2025target 2031
Solar project GEN-2024-153, Randall County
Solar
250 MWIn study Randall, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-368, Gray County
Battery storage
250 MWIn study Gray, TXSPP Mar 2025target 2028
Onshore wind project GEN-2024-145, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Onshore wind project GEN-2024-143, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Onshore wind project GEN-2024-134, Woods County
Onshore wind
250 MWIn study Woods, OKSPP Mar 2025target 2031
Battery storage project ERAS-2025-027, Yoakum County
Battery storage
250 MWIn study Yoakum, TXSPP Oct 2025target 2028
Gas project ERAS-2025-034, Jasper County
Gas
250 MWIn study Jasper, MOSPP Sep 2025target 2030
Onshore wind project GEN-2024-285, Clark County
Onshore wind
250 MWIn study Clark, SDSPP Mar 2025target 2030
Battery storage project GEN-2024-369, Grady County
Battery storage
250 MWIn study Grady, OKSPP Mar 2025target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)