Withdrawn queue requests in the USA (2022 requests) โ€” page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,886378.9 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,886 requests ยท page 17 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-111, Douglas County
Onshore wind
150 MWWithdrawn / abandoned Douglas, MOSoutheast Nov 2022target 2026
Solar project AH2-173, Ogle County
Solar
150 MWWithdrawn / abandoned Ogle, ILPJM Mar 2022target 2026
Solar + storage project 653, Bingham County
Solar + storage
150 MWWithdrawn / abandoned Bingham, IDWest Apr 2022
Solar project J1567, Outagamie County
Solar
150 MWWithdrawn / abandoned Outagamie, WIMISO Feb 2022target 2023
Solar project AH2-271, Mecklenburg County
Solar
150 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2022target 2026
Solar project J2939, Tunica County
Solar
150 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2025
Solar project J2547, Mccracken County
Solar
150 MWWithdrawn / abandoned Mccracken, KYMISO Sep 2022target 2027
Battery storage project GEN-2022-091, Mccurtain County
Battery storage
150 MWWithdrawn / abandoned Mccurtain, OKSPP Nov 2022target 2026
Solar project 137, Columbia County
Solar
150 MWWithdrawn / abandoned Columbia, WAWest Nov 2022target 2025
Solar project GEN-2022-008, Randall County
Solar
150 MWWithdrawn / abandoned Randall, TXSPP May 2022target 2028
Battery storage project C2-65, Salt Lake County
Battery storage
150 MWWithdrawn / abandoned Salt Lake, UTWest May 2022target 2024
Battery storage project Q25, Pinal County
Battery storage
150 MWWithdrawn / abandoned Pinal, AZWest Nov 2022target 2025
Solar
Solar
150 MWWithdrawn / abandoned Grafton, NHISO-NE Mar 2022target 2025
Battery storage project J2431, St. Francis County
Battery storage
150 MWWithdrawn / abandoned St. Francis, ARMISO Sep 2022target 2026
Solar project J2414, Vermilion County
Solar
150 MWWithdrawn / abandoned Vermilion, ILMISO Sep 2022target 2027
Onshore wind project J2435, Webster County
Onshore wind
150 MWWithdrawn / abandoned Webster, IAMISO Sep 2022target 2030
Solar project J2539, Clark County
Solar
150 MWWithdrawn / abandoned Clark, INMISO Sep 2022target 2026
Solar + storage project 113, Pima County
Solar + storage
150 MWWithdrawn / abandoned Pima, AZWest Feb 2022target 2026
Battery storage project Q34, Maricopa County
Battery storage
150 MWWithdrawn / abandoned Maricopa, AZWest Nov 2022target 2025
Onshore wind project J2434, Vermilion County
Onshore wind
150 MWWithdrawn / abandoned Vermilion, ILMISO Sep 2022target 2028
Solar + storage project Company MQ, Washoe County
Solar + storage
150 MWWithdrawn / abandoned Washoe, NVWest Mar 2022target 2022
Solar project J1965, Callaway County
Solar
150 MWWithdrawn / abandoned Callaway, MOMISO Mar 2022target 2025
Battery storage project AH2-279, Greene County
Battery storage
150 MWWithdrawn / abandoned Greene, PAPJM Mar 2022target 2024
Solar + storage project Company 215, Clark County
Solar + storage
150 MWWithdrawn / abandoned Clark, NVWest Mar 2022target 2026
Solar project AH2-273, Union County
Solar
150 MWWithdrawn / abandoned Union, OHPJM Mar 2022target 2026
Solar + storage project C2-205, Cache County
Solar + storage
150 MWWithdrawn / abandoned Cache, UTWest May 2022target 2026
Onshore wind project J2345, Marathon County
Onshore wind
150 MWWithdrawn / abandoned Marathon, WIMISO Sep 2022target 2028
Battery storage project C2-67, Salt Lake County
Battery storage
150 MWWithdrawn / abandoned Salt Lake, UTWest May 2022target 2024
Van Buren Storage
Battery storage ยท Origis Development
150 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2022
Battery storage project J2409, Independence County
Battery storage
150 MWWithdrawn / abandoned Independence, ARMISO Sep 2022target 2026
Solar + storage project LGE-GIS-2022-007, Lincoln County
Solar + storage
150 MWWithdrawn / abandoned Lincoln, KYSoutheast Sep 2022target 2026
Solar project GEN-2022-090, Mccurtain County
Solar
150 MWWithdrawn / abandoned Mccurtain, OKSPP Nov 2022target 2026
Solar + storage project J3225, Laporte County
Solar + storage
150 MWWithdrawn / abandoned Laporte, INMISO Sep 2022target 2026
Solar project J2433, Wadena County
Solar
150 MWWithdrawn / abandoned Wadena, MNMISO Sep 2022target 2027
Battery storage project C2-55, Lincoln County
Battery storage
150 MWWithdrawn / abandoned Lincoln, WYWest May 2022target 2024
Solar + storage project C2-64, Emery County
Solar + storage
150 MWWithdrawn / abandoned Emery, UTWest May 2022target 2024
Battery storage project J2438, Montgomery County
Battery storage
150 MWWithdrawn / abandoned Montgomery, MOMISO Sep 2022target 2027
Solar project J2748, Clearwater County
Solar
150 MWWithdrawn / abandoned Clearwater, MNMISO Sep 2022target 2026
Battery storage project J2872, Dakota County
Battery storage
150 MWWithdrawn / abandoned Dakota, MNMISO Sep 2022target 2025
Battery storage project J2658, Cumberland County
Battery storage
150 MWWithdrawn / abandoned Cumberland, ILMISO Sep 2022target 2026
Solar project J3017, Grant County
Solar
150 MWWithdrawn / abandoned Grant, SDMISO Sep 2022target 2027
Solar project J2925, Logan County
Solar
150 MWWithdrawn / abandoned Logan, ILMISO Sep 2022target 2026
Solar + storage project BHCT G38, Pueblo County
Solar + storage
150 MWWithdrawn / abandoned Pueblo, COWest Aug 2022target 2025
Battery storage project 22-118, Multnomah County
Battery storage
150 MWWithdrawn / abandoned Multnomah, ORWest Dec 2022target 2026
Solar project J2558, Sunflower County
Solar
150 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2027
Solar + storage project IC-1030, Mitchell County
Solar + storage
150 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2022
Solar + storage project J2803, Carroll County
Solar + storage
150 MWWithdrawn / abandoned Carroll, MSMISO Sep 2022target 2027
Solar + storage project J3016, Cass County
Solar + storage
150 MWWithdrawn / abandoned Cass, INMISO Sep 2022target 2027
Battery storage project J3123, Orange County
Battery storage
150 MWWithdrawn / abandoned Orange, TXMISO Sep 2022target 2026
Battery storage project Q454, Maricopa County
Battery storage
150 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)