🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA — page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,141423.2 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,141 requests · page 16 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Battery storage project 87, Skagit County
Battery storage
200 MWAgreement signed Skagit, WAWest Jul 2020target 2028
Battery storage project GEN-2024-SR11, Garfield County
Battery storage
200 MWAgreement signed Garfield, OKSPP May 20242025
Black Prairie Solar Park
Solar
200 MWAgreement signed White, INPJM Sep 2019target 2027
Solar + storage project Company LG, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar project J1525, Huron County
Solar
200 MWAgreement signed Huron, MIMISO Jun 2020target 2026
Solar project J1603, Otsego County
Solar
200 MWAgreement signed Otsego, MIMISO Dec 2021target 2025
Bottlebrush Solar
Solar
200 MWAgreement signed Lake, INPJM Jan 2019target 2028
Battery storage project Company 248, Clark County
Battery storage
200 MWAgreement signed Clark, NVWest Mar 2023target 2030
Onshore wind project BHBE G21, Campbell County
Onshore wind
200 MWAgreement signed Campbell, SDWest Aug 2022target 2025
Solar + storage project IC-839, Sumter County
Solar + storage
200 MWAgreement signed Sumter, GASoutheast Nov 2019target 2027
Battery storage project 98, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Mar 2021target 2026
Kestrel Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2027
Onshore wind project GI-2006-2, Logan County
Onshore wind
200 MWAgreement signed Logan, COWest Jun 2006target 2008
Onshore wind project GI-2011-7, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest Aug 2011target 2012
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Onshore wind project GI-2007-6, Weld County
Onshore wind
200 MWAgreement signed Weld, COWest Mar 2007target 2008
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Solar project J1576, Washington Parish County
Solar
200 MWAgreement signed Washington Parish, LAMISO Mar 2022target 2026
Solar project J1629, Columbia County
Solar
200 MWAgreement signed Columbia, WIMISO Jun 2020target 2027
Solar project IC-1195, Warren County
Solar
200 MWAgreement signed Warren, GASoutheast Oct 2023target 2028
Solar project J1481, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2025
Solar project IC-1204, Jefferson County
Solar
200 MWAgreement signed Jefferson, GASoutheast Nov 2023target 2028
Solar project J1196, Sanilac County
Solar
200 MWAgreement signed Sanilac, MIMISO Apr 2019target 2025
Battery storage project 17-067, Multnomah County
Battery storage
200 MWAgreement signed Multnomah, ORWest Sep 2017target 2031
Battery storage project Company NJ, Storey County
Battery storage
200 MWAgreement signed Storey, NVWest Mar 2022target 2026
Pleasant Prairie Solar Energy Center
Solar
200 MWAgreement signed Franklin, OHPJM Mar 2019target 2027
Solar project J1218, Muscatine County
Solar
200 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Battery storage project Company 197, Clark County
Battery storage
200 MWAgreement signed Clark, NVWest Mar 2021target 2024
Solar + storage project Company IL, Washoe County
Solar + storage
200 MWAgreement signed Washoe, NVWest Mar 2018target 2027
Solar project J1241, Jefferson County
Solar
200 MWAgreement signed Jefferson, ILMISO Apr 2019target 2024
Solar project 385, Lawrence County
Solar
200 MWAgreement signed Lawrence, ALSoutheast Aug 2019target 2026
Hudson Energy Storage Facility
Battery storage
200 MWAgreement signed Hudson, NJPJM Sep 2019target 2028
Onshore wind project BHBE G7, Campbell County
Onshore wind · Third Planet Wind
200 MWAgreement signed Campbell, SDWest Oct 2007target 2010
Solar + storage project Company 181, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2019target 2028
Solar project J1664, St. Clair County
Solar
200 MWAgreement signed St. Clair, MIMISO Jun 2020target 2026
Solar project J1215, Arkansas County
Solar
200 MWAgreement signed Arkansas, ARMISO Apr 2019target 2024
Solar project GEN-2019-016, Polk County
Solar
200 MWAgreement signed Polk, MOSPP Apr 2019target 2029
Battery storage project GEN-2023-SR8, Hansford County
Battery storage
200 MWAgreement signed Hansford, TXSPP Feb 2023target 2026
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Solar project J1379, Montcalm County
Solar
200 MWAgreement signed Montcalm, MIMISO Apr 2019target 2025
Co200B
Battery storage
200 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Solar project J1550, Branch County
Solar
200 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Battery storage project 21-102, Multnomah County
Battery storage
200 MWAgreement signed Multnomah, ORWest May 2021target 2030
Juan Tabo Grid
Battery storage
200 MWAgreement signed Bernalillo, NMWest Jun 2021target 2021
Battery storage project GEN-2019-012, Woodward County
Battery storage
200 MWAgreement signed Woodward, OKSPP May 2019target 2027
Solar project J1378, Fountain County
Solar
200 MWAgreement signed Fountain, INMISO Apr 2019target 2024
Old Route 66 Power
Solar
200 MWAgreement signed Guadalupe, NMWest Jun 2021target 2024
Solar project J1562, Mississippi County
Solar
200 MWAgreement signed Mississippi, ARMISO Jun 2020target 2025
Page 16 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)