Requests shown1,337302.2 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,337 requests · page 16 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J4069, Marathon County
Solar
170 MWIn study Marathon, WIMISO Oct 2025target 2030
Onshore wind project J1365, Tama County
Onshore wind
169 MWIn study Tama, IAMISO Apr 2019target 2024
Solar project J3053, Madison County
Solar
169 MWIn study Madison, MSMISO Sep 2022target 2024
Surplus; J291
Solar
169 MWIn study Scott, ILMISO Aug 2025target 2028
Wind + storage project J3962, Bay County
Wind + storage
165 MWIn study Bay, MIMISO Mar 2025target 2030
Solar project J1669, Jefferson Davis Parish County
Solar
165 MWIn study Jefferson Davis Parish, LAMISO Jun 2020target 2025
Solar project J2873, Simpson County
Solar
165 MWIn study Simpson, MSMISO Sep 2022target 2027
Solar project J3987, Amite County
Solar
165 MWIn study Amite, MSMISO Oct 2024target 2030
Solar project J1917, Livingston County
Solar
165 MWIn study Livingston, MIMISO Aug 2021target 2023
Onshore wind project J2576, Louisa County
Onshore wind
164 MWIn study Louisa, IAMISO Sep 2022target 2025
Onshore wind project J3900, Sunflower County
Onshore wind
163 MWIn study Sunflower, MSMISO Dec 2024target 2030
Onshore wind project E0036, Freeborn County
Onshore wind · Wisconsin Power and Light Company (WPL)
162 MWIn study Freeborn, MNMISO Aug 2025target 2028
Solar project J2714, St. Landry Parish County
Solar
162 MWIn study St. Landry Parish, LAMISO Sep 2022target 2027
Solar project J2757, Cherokee County
Solar
160 MWIn study Cherokee, IAMISO Oct 2025target 2026
Gas project J3152, Green County
Gas
160 MWIn study Green, WIMISO Sep 2022target 2027
Solar project J1619, Webster County
Solar
160 MWIn study Webster, KYMISO Jun 2020target 2024
Solar + storage project J3118, Morehouse Parish County
Solar + storage
160 MWIn study Morehouse Parish, LAMISO Sep 2022target 2026
Solar project J4047, Tuscola County
Solar
160 MWIn study Tuscola, MIMISO Aug 2025target 2028
Solar project J2608, Stevens County
Solar
160 MWIn study Stevens, MNMISO Sep 2022target 2026
Solar + storage project J2397, Calhoun County
Solar + storage
160 MWIn study Calhoun, ARMISO Sep 2022target 2025
Solar project J3827, Mackinac County
Solar
160 MWIn study Mackinac, MIMISO Apr 2024target 2028
Battery storage project J2997, Livingston County
Battery storage
160 MWIn study Livingston, MIMISO Sep 2022target 2025
Solar project J2651, East Baton Rouge Parish County
Solar
160 MWIn study East Baton Rouge Parish, LAMISO Sep 2022target 2026
Gas project J2946, Dubuque County
Gas
160 MWIn study Dubuque, IAMISO Sep 2022target 2027
Solar project J3731, Knox County
Solar
160 MWIn study Knox, INMISO Apr 2024target 2027
Gas project J3154, Franklin County
Gas
160 MWIn study Franklin, IAMISO Sep 2022target 2027
Gas project J3153, Clinton County
Gas
160 MWIn study Clinton, IAMISO Sep 2022target 2027
Solar + storage project J3742, Otter Tail County
Solar + storage
160 MWIn study Otter Tail, MNMISO Jun 2024target 2028
Solar project J3175, Tunica County
Solar
160 MWIn study Tunica, MSMISO Sep 2022target 2026
Solar project J2747, Greene County
Solar
160 MWIn study Greene, INMISO Sep 2022target 2026
Solar project J3064, Perry County
Solar
157 MWIn study Perry, ILMISO Sep 2022target 2026
Solar project J3137, Pocahontas County
Solar
156 MWIn study Pocahontas, IAMISO Oct 2025target 2026
Solar project J3442, Scott County
Solar
156 MWIn study Scott, MOMISO Apr 2024target 2028
Solar project J3461, Muscatine County
Solar
156 MWIn study Muscatine, IAMISO Apr 2024target 2028
Onshore wind project J3394, St. Landry Parish County
Onshore wind
156 MWIn study St. Landry Parish, LAMISO Apr 2024target 2027
Onshore wind project J3898, Howard County
Onshore wind
155 MWIn study Howard, IAMISO Feb 2025target 2030
Nuclear project J3815, St. Charles Parish County
Nuclear
153 MWIn study St. Charles Parish, LAMISO Jun 2024target 2026
Solar project J2561, Yellow Medicine County
Solar
153 MWIn study Yellow Medicine, MNMISO Sep 2022target 2030
Battery storage project J2378, Macomb County
Battery storage
152 MWIn study Macomb, MIMISO Sep 2022target 2026
Onshore wind project J2053, Redwood County
Onshore wind
152 MWIn study Redwood, MNMISO Aug 2021target 2025
Solar + storage project J3381, St. Francis County
Solar + storage
151 MWIn study St. Francis, ARMISO Apr 2024target 2028
Solar project J3682, Muskegon County
Solar
150 MWIn study Muskegon, MIMISO Apr 2024target 2028
Onshore wind project J2502, Morton County
Onshore wind
150 MWIn study Morton, NDMISO Sep 2022target 2025
Solar + storage project J2764, Craighead County
Solar + storage
150 MWIn study Craighead, ARMISO Jul 2025target 2025
Battery storage project J4083, Perry County
Battery storage
150 MWIn study Perry, MSMISO Oct 2025target 2030
Solar project J3471, Branch County
Solar
150 MWIn study Branch, MIMISO Apr 2024target 2028
Solar + storage project J3745, Dearborn County
Solar + storage
150 MWIn study Dearborn, INMISO Apr 2024target 2028
Onshore wind project J1967, Champaign County
Onshore wind
150 MWIn study Champaign, ILMISO Mar 2022target 2025
Solar project J1783, Montgomery County
Solar
150 MWIn study Montgomery, INMISO Jun 2020target 2025
Battery storage project J3543, Dakota County
Battery storage
150 MWIn study Dakota, MNMISO Apr 2024target 2028
Page 16 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)