🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arkansas

SOLAR + STORAGE · MISO

Solar + storage project J3381, St. Francis County

Solar + storage project J3381, St. Francis County is a 151 MW solar + storage request in interconnection study in the MISO interconnection queue, in St. Francis County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3381
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
FORREST CITY SOUTH - HUGHES 161.0kV
Location
St. Francis County, Arkansas
Technology
Solar: 151 MW · Battery
Total requested
151 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
18 April 2024
Proposed online date
January 2028
Withdrawn
January 2026

Location

Marker shows the centre of St. Francis County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in St. Francis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem