Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 15 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Garrard Solar
Solar · PJM Solar Devco I, LLC
222 MWWithdrawn / abandoned Garrard, KYPJM Sep 2020target 2023
Gas project U1-036, Baltimore County
Gas
220 MWWithdrawn / abandoned Baltimore, MDPJM Feb 2008target 2011
Gas project AA2-077, Philadelphia County
Gas
220 MWWithdrawn / abandoned Philadelphia, PAPJM Mar 2015target 2018
Solar project AF2-217, Union County
Solar
220 MWWithdrawn / abandoned Union, OHPJM Mar 2020target 2024
Solar + storage project AF1-251, Clark County
Solar + storage
220 MWWithdrawn / abandoned Clark, KYPJM Sep 2019target 2023
Battery storage project AG2-450, Gloucester County
Battery storage · Logan Energy Storage, L.L.C.
219 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2025target 2025
Gas project Y2-083, Essex County
Gas
218 MWWithdrawn / abandoned Essex, NJPJM Oct 2012target 2016
Gas project W3-173, New Castle County
Gas
218 MWWithdrawn / abandoned New Castle, DEPJM Oct 2010target 2015
Gas project Z1-034, Trumbull County
Gas
217 MWWithdrawn / abandoned Trumbull, OHPJM Jul 2013target 2017
Gas project AH1-749
Gas · East Kentucky Power Cooperative, Inc.
216 MWWithdrawn / abandoned KYPJM target 2028
Beech Hollow Solar
Solar
215 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2020target 2028
Solar project AG2-687, Garrard County
Solar
215 MWWithdrawn / abandoned Garrard, KYPJM Mar 2021target 2024
Solar project AG2-686, Nicholas County
Solar
215 MWWithdrawn / abandoned Nicholas, WVPJM Mar 2021target 2024
Onshore wind project Z2-007, Carbon County
Onshore wind
213 MWWithdrawn / abandoned Carbon, PAPJM Nov 2013target 2015
Onshore wind project AG2-674, Whiteside County
Onshore wind
212 MWWithdrawn / abandoned Whiteside, ILPJM Mar 2021target 2023
Onshore wind project AF1-314, Stephenson County
Onshore wind · High Point Wind Farm, LLC
212 MWWithdrawn / abandoned Stephenson, ILPJM Sep 2019target 2022
Onshore wind project AF2-267, Stephenson County
Onshore wind
211 MWWithdrawn / abandoned Stephenson, ILPJM Mar 2020target 2022
Solar project AG2-658, Webster County
Solar · Halo Solar WV LLC
210 MWWithdrawn / abandoned Webster, WVPJM Jan 2025target 2024
Gas project AA2-050, Philadelphia County
Gas
210 MWWithdrawn / abandoned Philadelphia, PAPJM Feb 2015target 2018
Coal project R70, Gallia County
Coal
210 MWWithdrawn / abandoned Gallia, OHPJM Jan 2007target 1980
Solar project AG1-224, Fayette County
Solar · RUSH SOLAR PROJECT II, LLC
210 MWWithdrawn / abandoned Fayette, INPJM Sep 2020target 2023
Walnut Ridge Wind Farm
Onshore wind
210 MWWithdrawn / abandoned Bureau, ILPJM Oct 2005target 2017
Battery storage project AE2-330, Mchenry County
Battery storage
209 MWWithdrawn / abandoned Mchenry, ILPJM Mar 2019target 2021
Battery storage project AE2-340, Kendall County
Battery storage
209 MWWithdrawn / abandoned Kendall, ILPJM Mar 2019target 2022
Battery storage project AE2-332, Elkhart County
Battery storage
209 MWWithdrawn / abandoned Elkhart, INPJM Mar 2019target 2021
Battery storage project AE2-329, Clermont County
Battery storage
209 MWWithdrawn / abandoned Clermont, OHPJM Mar 2019target 2022
Solar project AD2-193, Spotsylvania County
Solar
209 MWWithdrawn / abandoned Spotsylvania, VAPJM Mar 2018target 2020
Onshore wind project AA1-103, Carbon County
Onshore wind
209 MWWithdrawn / abandoned Carbon, PAPJM Oct 2014target 2016
Gas project Z1-109, Union County
Gas
208 MWWithdrawn / abandoned Union, NJPJM Oct 2013target 2016
Gas project Z2-084, Nelson County
Gas
208 MWWithdrawn / abandoned Nelson, KYPJM Apr 2014target 2016
Onshore wind project W3-046, Mason County
Onshore wind
208 MWWithdrawn / abandoned Mason, ILPJM Aug 2010target 2015
Gas project AE2-288, Snyder County
Gas
206 MWWithdrawn / abandoned Snyder, PAPJM Mar 2019target 2023
Gas project T44, Essex County
Gas
205 MWWithdrawn / abandoned Essex, NJPJM Sep 2007target 2014
Battery storage project AH1-765, Morrow County
Battery storage · NextEra Energy Resources Interconnection Holdings, LLC
205 MWWithdrawn / abandoned Morrow, OHPJM target 2029
Solar project AD2-177, Livingston County
Solar
205 MWWithdrawn / abandoned Livingston, ILPJM Mar 2018target 2021
Gas project Y2-065, Beaver County
Gas
205 MWWithdrawn / abandoned Beaver, PAPJM Sep 2012target 2017
Gas project T45, Hudson County
Gas
205 MWWithdrawn / abandoned Hudson, NJPJM Sep 2007target 2011
Solar + storage project AE1-247, Barren County
Solar + storage
205 MWWithdrawn / abandoned Barren, KYPJM Sep 2018target 2022
Battery storage project AH1-766, Highland County
Battery storage · NextEra Energy Resources Interconnection Holdings, LLC
205 MWWithdrawn / abandoned Highland, OHPJM target 2029
Solar project AD2-175, Kankakee County
Solar
205 MWWithdrawn / abandoned Kankakee, ILPJM Mar 2018target 2021
Other project Z2-072
Other
205 MWWithdrawn / abandoned PJM Apr 2014
Solar + storage project AF1-142, Clearfield County
Solar + storage · Moonlight Flats Solar Power, LLC
202 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2019target 2022
Firefly Solar
Solar
202 MWWithdrawn / abandoned Lawrence, PAPJM Sep 2019target 2026
Solar project AG2-680, Madison County
Solar
202 MWWithdrawn / abandoned Madison, VAPJM Mar 2021target 2024
Onshore wind project V2-022, Morrow County
Onshore wind
201 MWWithdrawn / abandoned Morrow, OHPJM Jun 2009target 2012
Gas project O64, Philadelphia County
Gas
201 MWWithdrawn / abandoned Philadelphia, PAPJM Jul 2005target 2008
Onshore wind project Q60, Henry County
Onshore wind
201 MWWithdrawn / abandoned Henry, ILPJM Jul 2006target 2009
Onshore wind project U2-042, Hardin County
Onshore wind
201 MWWithdrawn / abandoned Hardin, OHPJM Jun 2008target 2011
Onshore wind project AC1-226, Pulaski County
Onshore wind
200 MWWithdrawn / abandoned Pulaski, VAPJM Oct 2016target 2019
Solar + storage project AE1-135, Greensville County
Solar + storage
200 MWWithdrawn / abandoned Greensville, VAPJM Sep 2018target 2019
Page 15 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)