United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 15
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Garrard Solar Solar · PJM Solar Devco I, LLC |
222 MW | Withdrawn / abandoned |
| Gas project U1-036, Baltimore County Gas |
220 MW | Withdrawn / abandoned |
| Gas project AA2-077, Philadelphia County Gas |
220 MW | Withdrawn / abandoned |
| Solar project AF2-217, Union County Solar |
220 MW | Withdrawn / abandoned |
| Solar + storage project AF1-251, Clark County Solar + storage |
220 MW | Withdrawn / abandoned |
| Battery storage project AG2-450, Gloucester County Battery storage · Logan Energy Storage, L.L.C. |
219 MW | Withdrawn / abandoned |
| Gas project Y2-083, Essex County Gas |
218 MW | Withdrawn / abandoned |
| Gas project W3-173, New Castle County Gas |
218 MW | Withdrawn / abandoned |
| Gas project Z1-034, Trumbull County Gas |
217 MW | Withdrawn / abandoned |
| Gas project AH1-749 Gas · East Kentucky Power Cooperative, Inc. |
216 MW | Withdrawn / abandoned |
| Beech Hollow Solar Solar |
215 MW | Withdrawn / abandoned |
| Solar project AG2-687, Garrard County Solar |
215 MW | Withdrawn / abandoned |
| Solar project AG2-686, Nicholas County Solar |
215 MW | Withdrawn / abandoned |
| Onshore wind project Z2-007, Carbon County Onshore wind |
213 MW | Withdrawn / abandoned |
| Onshore wind project AG2-674, Whiteside County Onshore wind |
212 MW | Withdrawn / abandoned |
| Onshore wind project AF1-314, Stephenson County Onshore wind · High Point Wind Farm, LLC |
212 MW | Withdrawn / abandoned |
| Onshore wind project AF2-267, Stephenson County Onshore wind |
211 MW | Withdrawn / abandoned |
| Solar project AG2-658, Webster County Solar · Halo Solar WV LLC |
210 MW | Withdrawn / abandoned |
| Gas project AA2-050, Philadelphia County Gas |
210 MW | Withdrawn / abandoned |
| Coal project R70, Gallia County Coal |
210 MW | Withdrawn / abandoned |
| Solar project AG1-224, Fayette County Solar · RUSH SOLAR PROJECT II, LLC |
210 MW | Withdrawn / abandoned |
| Walnut Ridge Wind Farm Onshore wind |
210 MW | Withdrawn / abandoned |
| Battery storage project AE2-330, Mchenry County Battery storage |
209 MW | Withdrawn / abandoned |
| Battery storage project AE2-340, Kendall County Battery storage |
209 MW | Withdrawn / abandoned |
| Battery storage project AE2-332, Elkhart County Battery storage |
209 MW | Withdrawn / abandoned |
| Battery storage project AE2-329, Clermont County Battery storage |
209 MW | Withdrawn / abandoned |
| Solar project AD2-193, Spotsylvania County Solar |
209 MW | Withdrawn / abandoned |
| Onshore wind project AA1-103, Carbon County Onshore wind |
209 MW | Withdrawn / abandoned |
| Gas project Z1-109, Union County Gas |
208 MW | Withdrawn / abandoned |
| Gas project Z2-084, Nelson County Gas |
208 MW | Withdrawn / abandoned |
| Onshore wind project W3-046, Mason County Onshore wind |
208 MW | Withdrawn / abandoned |
| Gas project AE2-288, Snyder County Gas |
206 MW | Withdrawn / abandoned |
| Gas project T44, Essex County Gas |
205 MW | Withdrawn / abandoned |
| Battery storage project AH1-765, Morrow County Battery storage · NextEra Energy Resources Interconnection Holdings, LLC |
205 MW | Withdrawn / abandoned |
| Solar project AD2-177, Livingston County Solar |
205 MW | Withdrawn / abandoned |
| Gas project Y2-065, Beaver County Gas |
205 MW | Withdrawn / abandoned |
| Gas project T45, Hudson County Gas |
205 MW | Withdrawn / abandoned |
| Solar + storage project AE1-247, Barren County Solar + storage |
205 MW | Withdrawn / abandoned |
| Battery storage project AH1-766, Highland County Battery storage · NextEra Energy Resources Interconnection Holdings, LLC |
205 MW | Withdrawn / abandoned |
| Solar project AD2-175, Kankakee County Solar |
205 MW | Withdrawn / abandoned |
| Other project Z2-072 Other |
205 MW | Withdrawn / abandoned |
| Solar + storage project AF1-142, Clearfield County Solar + storage · Moonlight Flats Solar Power, LLC |
202 MW | Withdrawn / abandoned |
| Firefly Solar Solar |
202 MW | Withdrawn / abandoned |
| Solar project AG2-680, Madison County Solar |
202 MW | Withdrawn / abandoned |
| Onshore wind project V2-022, Morrow County Onshore wind |
201 MW | Withdrawn / abandoned |
| Gas project O64, Philadelphia County Gas |
201 MW | Withdrawn / abandoned |
| Onshore wind project Q60, Henry County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project U2-042, Hardin County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project AC1-226, Pulaski County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar + storage project AE1-135, Greensville County Solar + storage |
200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)