πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

BATTERY STORAGE Β· PJM

Battery storage project AE2-332, Elkhart County

Battery storage project AE2-332, Elkhart County is a 209 MW battery storage request withdrawn in the PJM interconnection queue, in Elkhart County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE2-332
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Twin Branch-Guardian 138 kV
Location
Elkhart County, Indiana
Technology
Battery: 209 MW
Total requested
209 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 March 2019
Proposed online date
December 2021
Withdrawn
April 2019

Location

Marker shows the centre of Elkhart County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Elkhart County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem