United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
GAS Β· PJMGas project AH1-749
Gas project AH1-749 is a 216 MW gas request withdrawn in the PJM interconnection queue, connecting to EKPC.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-749
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- East Kentucky Power Cooperative, Inc.
- Location
- Kentucky
- Technology
- Gas: 216 MW
- Total requested
- 216 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Proposed online date
- December 2028
- Withdrawn
- May 2025
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem