πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

GAS Β· PJM

Gas project AH1-749

Gas project AH1-749 is a 216 MW gas request withdrawn in the PJM interconnection queue, connecting to EKPC.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-749
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Developer
East Kentucky Power Cooperative, Inc.
Location
Kentucky
Technology
Gas: 216 MW
Total requested
216 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Proposed online date
December 2028
Withdrawn
May 2025

Location

No county location in the queue data.

Power plants in Kentucky Β· Transmission lines in Kentucky

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem