United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in CAISO (California) — page 14
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Robin 2 Solar + storage |
308 MW | Withdrawn / abandoned |
| Hinson BESS Battery storage |
308 MW | Withdrawn / abandoned |
| Genoa Energy Storage 2 Battery storage |
308 MW | Withdrawn / abandoned |
| Baylands Power Bank Battery storage |
308 MW | Withdrawn / abandoned |
| Casy Solar Solar + storage |
308 MW | Withdrawn / abandoned |
| Hog Island Solar + storage |
307 MW | Withdrawn / abandoned |
| Vantage Battery storage |
307 MW | Withdrawn / abandoned |
| Mountain Valley Storage Battery storage |
306 MW | Withdrawn / abandoned |
| Warm Water Battery storage |
306 MW | Withdrawn / abandoned |
| Barbosa Battery storage |
306 MW | Withdrawn / abandoned |
| Grape Valley Storage Battery storage |
306 MW | Withdrawn / abandoned |
| Copernicus Solar + storage |
306 MW | Withdrawn / abandoned |
| Nikola Norte Solar + storage |
306 MW | Withdrawn / abandoned |
| Hidden Hills Solar 1 Solar |
306 MW | Withdrawn / abandoned |
| Tesoster Solar + storage |
306 MW | Withdrawn / abandoned |
| Nikovaster Solar + storage |
306 MW | Withdrawn / abandoned |
| Muir Storage Battery storage |
305 MW | Withdrawn / abandoned |
| Sevillano Solar |
305 MW | Withdrawn / abandoned |
| Mission Rock Energy Center (Fka Mission Rock Energy Center Flex) Gas |
305 MW | Withdrawn / abandoned |
| Superba Storage 1 Battery storage |
305 MW | Withdrawn / abandoned |
| Epps Storage Battery storage |
305 MW | Withdrawn / abandoned |
| Heartland PV Solar |
305 MW | Withdrawn / abandoned |
| Flamingo Battery storage |
304 MW | Withdrawn / abandoned |
| Sciurus Battery storage |
304 MW | Withdrawn / abandoned |
| Paladin Battery storage |
304 MW | Withdrawn / abandoned |
| Arcturus Solar + storage |
304 MW | Withdrawn / abandoned |
| Vernon Power Plant Expansion Project Gas |
304 MW | Withdrawn / abandoned |
| Marcus Storage Battery storage |
304 MW | Withdrawn / abandoned |
| Ace Battery storage |
304 MW | Withdrawn / abandoned |
| Amber Ray Battery storage |
304 MW | Withdrawn / abandoned |
| Finke River Solar + storage |
304 MW | Withdrawn / abandoned |
| Balsam Solar + storage |
304 MW | Withdrawn / abandoned |
| Sugarloaf Hybrid Solar Solar + storage |
303 MW | Withdrawn / abandoned |
| Dunnigan Onshore wind |
301 MW | Withdrawn / abandoned |
| Dutchmans Pass Solar + storage |
301 MW | Withdrawn / abandoned |
| Cordelia Hills Wind Power Plant Onshore wind |
301 MW | Withdrawn / abandoned |
| Barren Ridge II Onshore wind |
300 MW | Withdrawn / abandoned |
| Nevada 300 Solar |
300 MW | Withdrawn / abandoned |
| Desert Quartzite Solar Solar |
300 MW | Withdrawn / abandoned |
| Hyder Valley Solar Energy Solar |
300 MW | Withdrawn / abandoned |
| Enn Mojave Power 4 Other |
300 MW | Withdrawn / abandoned |
| Troy Lake Soleil Solar |
300 MW | Withdrawn / abandoned |
| Eagle Mountain Solar |
300 MW | Withdrawn / abandoned |
| Pachacamac 2 Battery storage |
300 MW | Withdrawn / abandoned |
| Separator Unit 2 Battery storage |
300 MW | Withdrawn / abandoned |
| Delilah Energy Storage 2 Battery storage |
300 MW | Withdrawn / abandoned |
| Calcium Energy Storage Battery storage |
300 MW | Withdrawn / abandoned |
| PVV-M Solar I Solar |
300 MW | Withdrawn / abandoned |
| Pachacamac 1 Battery storage |
300 MW | Withdrawn / abandoned |
| Speedway ESS 2 Battery storage |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)