Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,272255.2 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,272 requests ยท page 13 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Tejano Storage
Battery storage ยท Tejano Storage, LLC
152 MWIn study Victoria, TXERCOT Mar 2022target 2029
Battery storage project J2378, Macomb County
Battery storage
152 MWIn study Macomb, MIMISO Sep 2022target 2026
Palladium Storage
Battery storage ยท Palladium Energy Storage LLC
152 MWIn study Hidalgo, TXERCOT Feb 2022target 2028
Violet Storage
Battery storage ยท VIOLET STORAGE
151 MWIn study Nueces, TXERCOT May 2022target 2029
Bottom Grass BESS II
Solar + storage ยท Flint Rock Solar Project, LLC
151 MWIn study Colorado, TXERCOT Nov 2022target 2028
Onshore wind project J2502, Morton County
Onshore wind
150 MWIn study Morton, NDMISO Sep 2022target 2025
Battery storage project AH2-377, Grundy County
Battery storage
150 MWIn study Grundy, ILPJM Mar 2022target 2024
Onshore wind project J1967, Champaign County
Onshore wind
150 MWIn study Champaign, ILMISO Mar 2022target 2025
Solar project J2740, Sunflower County
Solar
150 MWIn study Sunflower, MSMISO Sep 2022target 2029
Solara BESS 2
Battery storage ยท CED Development Inc.
150 MWIn study Jones, TXERCOT Jul 2022target 2027
Battery storage project AI2-001, Caroline County
Battery storage
150 MWIn study Caroline, VAPJM Oct 2022target 2028
Solar project J2678, Delta County
Solar
150 MWIn study Delta, MIMISO Sep 2022target 2025
Solar + storage project 2022-G11, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Aug 2022target 2025
San Perlita BESS 1
Battery storage ยท RWE Renewables
150 MWIn study Willacy, TXERCOT Jun 2022target 2025
Solar + storage project J2389, Adams County
Solar + storage
150 MWIn study Adams, ILMISO Sep 2022target 2026
Battery storage project 147, Pima County
Battery storage
150 MWIn study Pima, AZWest Dec 2022target 2026
Battery storage project J2731, Olmsted County
Battery storage
150 MWIn study Olmsted, MNMISO Sep 2022target 2025
Solar + storage project J2869, Sunflower County
Solar + storage
150 MWIn study Sunflower, MSMISO Sep 2022target 2027
Onshore wind project C2-49, Converse County
Onshore wind
150 MWIn study Converse, WYWest May 2022target 2026
Solar + storage project BHCT G35, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest Aug 2022target 2026
Battery storage project AH2-077, Sussex County
Battery storage
150 MWIn study Sussex, DEPJM Jan 2022target 2027
Solar + storage project 2022-G10, Pinal County
Solar + storage
150 MWIn study Pinal, AZWest Jul 2022target 2025
Solar project J3145, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027
Solar project J3144, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027
Onshore wind project J2686, Muscatine County
Onshore wind
150 MWIn study Muscatine, IAMISO Sep 2022target 2026
Solar project J2875, Presque Isle County
Solar
150 MWIn study Presque Isle, MIMISO Sep 2022target 2025
Solar project AH2-350, Cumberland County
Solar
150 MWIn study Cumberland, VAPJM Mar 2022target 2025
Battery storage project 640, Ada County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
150 MWPaused / redesign Ada, IDWest Feb 2022target 2026
Battery storage project J2326, Outagamie County
Battery storage
150 MWIn study Outagamie, WIMISO Sep 2022target 2025
Solar + storage project IC-1100, Pulaski County
Solar + storage
150 MWPaused / redesign Pulaski, GASoutheast Nov 2022target 2026
Solar + storage project IC-1101, Perry County
Solar + storage
150 MWPaused / redesign Perry, ALSoutheast Dec 2022target 2027
Solar + storage project J2880, Jefferson County
Solar + storage
150 MWIn study Jefferson, ARMISO Sep 2022target 2026
Solar project J2401, Johnson County
Solar
150 MWIn study Johnson, ILMISO Sep 2022target 2025
Battery storage project 27, Sacramento County
Battery storage
150 MWIn study Sacramento, CAWest Oct 2022target 2027
Solar project J1566, Martin County
Solar
150 MWIn study Martin, MNMISO Feb 2022target 2026
Battery storage project J2730, Jackson County
Battery storage
150 MWIn study Jackson, MNMISO Sep 2022target 2025
Solar project IC-1037, Taliaferro County
Solar
150 MWPaused / redesign Taliaferro, GASoutheast May 2022target 2026
Battery storage project AI1-166, Cass County
Battery storage
150 MWIn study Cass, MIPJM Sep 2022target 2028
Solar project PIS027, Utah County
Solar
150 MWIn study Utah, UTWest Jul 2022target 2025
Solar project J2749, Polk County
Solar
150 MWIn study Polk, MNMISO Sep 2022target 2026
Battery storage project AI2-002, Washington County
Battery storage
150 MWIn study Washington, VAPJM Oct 2022target 2028
Solar project J2643, Washington Parish County
Solar
150 MWIn study Washington Parish, LAMISO Sep 2022target 2027
Battery storage project AH2-144, King George County
Battery storage
150 MWIn study King George, VAPJM Feb 2022target 2027
Solar + storage project 2023-G2
Solar + storage
150 MWIn study West Nov 2022target 2026
Solar + storage project AH2-154, Vermillion County
Solar + storage
150 MWIn study Vermillion, INPJM Feb 2022target 2024
Solar project 2023-G3
Solar
150 MWIn study West Nov 2022target 2026
Solar + storage project Q463, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Mar 2022target 2024
Battery storage project J2728, Freeborn County
Battery storage
150 MWIn study Freeborn, MNMISO Sep 2022target 2025
Battery storage project J2627, Adams County
Battery storage
150 MWIn study Adams, ILMISO Sep 2022target 2025
Battery storage project 122, Pinal County
Battery storage
150 MWIn study Pinal, AZWest May 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)