Tejano Storage

Tejano Storage is a 152 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Victoria County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0168
Grid region
ERCOT (Texas)
Developer
Tejano Storage, LLC
Connection point (POI)
Tap 138kV 8125 Lolita - 8172 Victoria
Location
Victoria County, Texas
Technology
Battery: 152 MW
Total requested
152 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
30 March 2022
Proposed online date
July 2029

Location

Marker shows the centre of Victoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Victoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem