Withdrawn queue requests in CAISO (California) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 13 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Collis
Solar + storage
321 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Morning Star
Solar + storage
321 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Occident
Solar + storage
321 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Buckhorn
Solar + storage
321 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Salome
Solar + storage
321 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Luz Solar Partners
Solar
320 MWWithdrawn / abandoned San Bernardino, CACAISO Nov 2006target 2009
Wre - Vestal (49/480MW)
Solar
320 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2013
Kanoa Solar
Solar + storage
320 MWWithdrawn / abandoned Glenn, CACAISO Apr 2021target 2031
Callinan Solar And Storage
Solar + storage
320 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2031
Tule Fog Solar
Solar + storage
317 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
CPV California III
Gas
315 MWWithdrawn / abandoned San Diego, CACAISO Apr 2007target 2010
Yellowfin
Battery storage
315 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
CPV California IV
Gas
315 MWWithdrawn / abandoned San Diego, CACAISO Apr 2007target 2010
CPV California V
Gas
315 MWWithdrawn / abandoned San Diego, CACAISO Apr 2007target 2011
Island Energy Center
Gas
315 MWWithdrawn / abandoned San Joaquin, CACAISO May 2008target 2012
Tamalpais Energy Storage
Battery storage
314 MWWithdrawn / abandoned Marin, CACAISO Apr 2021target 2030
Borealis Energy Storage
Battery storage
314 MWWithdrawn / abandoned Sonoma, CACAISO Apr 2021target 2030
Wardenclyffe
Battery storage
314 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2022
Parachute
Battery storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Monkey Flower
Battery storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Tortuga
Battery storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Crossroads 2
Battery storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Luzen Solar Energy Center
Solar + storage
313 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2020target 2022
Farm Bell Energy Center
Solar + storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Crossroads Storage
Battery storage
313 MWWithdrawn / abandoned Shasta, CACAISO Apr 2020target 2027
North Almond Energy Center
Solar + storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Desert Senna Energy Center
Solar + storage
313 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Harquahala Sun
Solar + storage
313 MWWithdrawn / abandoned Maricopa, AZCAISO May 2017target 2020
Silverwing
Solar + storage
312 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Bounty (Formly East Kern Hybrid)
Solar + storage
311 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Clarion Energy Center
Battery storage
311 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Pelican Island
Solar
311 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Century Solar
Solar
310 MWWithdrawn / abandoned Maricopa, AZCAISO May 2016target 2021
Fort Mojave Solar
Solar
310 MWWithdrawn / abandoned Mojave, AZCAISO Feb 2010target 2019
Badger Flat
Battery storage
310 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Prospect Energy Center
Gas
310 MWWithdrawn / abandoned Yuba, CACAISO Apr 2012target 2017
Twilight
Solar + storage
310 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Homestead Energy Center
Battery storage
310 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Redpoint
Solar + storage
310 MWWithdrawn / abandoned Kings, CACAISO Apr 2023target 2028
Anacapa
Solar + storage
309 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2020target 2023
Sand Solar
Solar
309 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2021
Key Storage 2
Battery storage
309 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2024
Diablo Energy Facility
Gas
309 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2014target 2017
Marnier
Solar + storage
309 MWWithdrawn / abandoned Merced, CACAISO Apr 2021target 2024
HillRich
Battery storage
309 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2023target 2028
Barrenspring
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Vestal Valley
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Japatul Valley Storage
Battery storage
308 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2024
San Bernardino BESS
Battery storage
308 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2022
Syrah Storage Center
Battery storage
308 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Page 13 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)