United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,067161.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,067 requests · page 11 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 568892, Darlington County
Solar · Duke Energy Progress, LLC
76.0 MWAgreement signed Darlington, SCSoutheast Jun 2022target 2027
Scarboro Solar
Solar + storage
75.0 MWIn study Miller, GASoutheast Dec 2024target 2031
Solar project 565080, Darlington County
Solar
75.0 MWAgreement signed Darlington, SCSoutheast Jun 2022
Solar project 167, Darlington County
Solar
75.0 MWPaused / redesign Darlington, SCSoutheast Oct 2021target 2025
Solar project 20220112001, Hampton County
Solar · Greenbow Solar Park LLC
75.0 MWIn study Hampton, SCSoutheast target 2026
Solar project 238, Marion County
Solar
75.0 MWIn study Marion, SCSoutheast Jun 2023target 2027
Solar project PP00007, Darlington County
Solar
75.0 MWIn study Darlington, SCSoutheast Dec 2024target 2027
Solar project 570382, Darlington County
Solar
75.0 MWAgreement signed Darlington, SCSoutheast Jun 2022target 2028
Gas project GI-102, Clinton County
Gas
75.0 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Battery storage project 234, Hampton County
Battery storage
75.0 MWIn study Hampton, SCSoutheast Jun 2023target 2027
Solar project 920665, Union County
Solar
75.0 MWAgreement signed Union, SCSoutheast Sep 2023
Battery storage project 20211221001, Hampton County
Battery storage
75.0 MWIn study Hampton, SCSoutheast target 2024
Solar project 246, Williamsburg County
Solar
75.0 MWIn study Williamsburg, SCSoutheast Feb 2024target 2028
Solar project 956538, Marlboro County
Solar
75.0 MWIn study Marlboro, SCSoutheast Jun 2024
Solar + storage project 425A, Jackson County
Solar + storage · Third Party
75.0 MWAgreement signed Jackson, FLSoutheast Feb 2022target 2029
Solar project 20250929001, Fairfield County
Solar
75.0 MWIn study Fairfield, SCSoutheast target 2030
Solar project 25-IC-1360, Sumter County
Solar
75.0 MWIn study Sumter, ALSoutheast Apr 2025target 2029
Gas project LGE-GIS-2024-002, Hopkins County
Gas
75.0 MWAgreement signed Hopkins, KYSoutheast Feb 2024target 2027
Battery storage project 251, Williamsburg County
Battery storage
75.0 MWIn study Williamsburg, SCSoutheast Feb 2024target 2028
Solar project 20220429001, Calhoun County
Solar · Leek Holdings, LLC
75.0 MWIn study Calhoun, SCSoutheast target 2026
Solar + storage project 671, Monroe County
Solar + storage
75.0 MWIn study Monroe, MSSoutheast Oct 2024target 2029
Solar project 132, Hampton County
Solar
75.0 MWIn study Hampton, SCSoutheast Dec 2019target 2024
Solar project 344, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Madison, FLSoutheast Jan 2024target 2026
Solar project 259, Highlands County
Solar · Placid Solar II, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 566724, Darlington County
Solar
74.9 MWUnder construction Darlington, SCSoutheast Jun 2022target 2026
Solar project 218, Suwannee County
Solar · Twin Rivers Solar, LLC
74.9 MWIn study Suwannee, FLSoutheast Feb 2018target 2020
Solar project 605, Desoto County
Solar · FPL
74.9 MWIn study Desoto, FLSoutheast Dec 2023target 2032
Solar project PP00002, Darlington County
Solar
74.9 MWUnder construction Darlington, SCSoutheast Sep 2024target 2026
Solar project 925531, Williamsburg County
Solar
74.9 MWUnder construction Williamsburg, SCSoutheast Jun 2021target 2026
Solar project FC100384, Suwannee County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project 343, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2028
Solar project 208, Aiken County
Solar
74.9 MWIn study Aiken, SCSoutheast Jun 2023target 2026
Solar project 977882, Cumberland County
Solar
74.9 MWIn study Cumberland, NCSoutheast Jun 2025
Solar project FC100007, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Solar + storage project 20230829011, Saluda County
Solar + storage
74.9 MWIn study Saluda, SCSoutheast target 2027
Solar project 566488, Chesterfield County
Solar
74.9 MWUnder construction Chesterfield, SCSoutheast Jun 2022target 2027
Solar project 326, Osceola County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2027
Solar project 604, Desoto County
Solar · FPL
74.9 MWIn study Desoto, FLSoutheast Dec 2023target 2032
Solar project FC100018, Liberty County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2024target 2028
Solar project 307, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 342, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2027
Solar project PP00004, Darlington County
Solar
74.9 MWIn study Darlington, SCSoutheast Sep 2024target 2027
Solar project 258, Highlands County
Solar · Placid Solar, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Battery storage project 230, Williamsburg County
Battery storage
74.9 MWIn study Williamsburg, SCSoutheast Jun 2023target 2028
Solar + storage project JEA-Q012, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2027
Other project PP00057, Marlboro County
Other
74.9 MWIn study Marlboro, SCSoutheast Nov 2025target 2028
Solar + storage project JEA-Q010, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2026
Solar project 957368, Marlboro County
Solar
74.9 MWIn study Marlboro, SCSoutheast Jun 2024
Solar project FC100012, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Hamilton, FLSoutheast Nov 2024target 2028
Solar project 323, Jackson County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Jackson, FLSoutheast Feb 2023target 2027
Page 11 of 22

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)