United States › Grid › Interconnection queues › South Carolina

SOLAR + STORAGE · SOUTHEAST

Solar + storage project 20230829011, Saluda County

Solar + storage project 20230829011, Saluda County is a 74.9 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Saluda County, South Carolina, connecting to Dominion Energy South Carolina.

Queue statusIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
20230829011
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Dominion Energy South Carolina
Connection point (POI)
Graniteville – Ward 230 kV
Location
Saluda County, South Carolina
Technology
Solar: 74.9 MW · Battery
Total requested
74.9 MW
Queue status
Active
Proposed online date
June 2027

Location

Marker shows the centre of Saluda County; the queue data does not give exact sites.

Power plants in South Carolina · Transmission lines in South Carolina

Other requests in Saluda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem