United States › Grid › Interconnection queues › South Carolina
SOLAR + STORAGE · SOUTHEASTSolar + storage project 20230829011, Saluda County
Solar + storage project 20230829011, Saluda County is a 74.9 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Saluda County, South Carolina, connecting to Dominion Energy South Carolina.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 20230829011
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Dominion Energy South Carolina
- Connection point (POI)
- Graniteville – Ward 230 kV
- Location
- Saluda County, South Carolina
- Technology
- Solar: 74.9 MW · Battery
- Total requested
- 74.9 MW
- Queue status
- Active
- Proposed online date
- June 2027
Location
Marker shows the centre of Saluda County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Saluda County
- Solar project 267, Saluda CountySolar · 186 MW · in study
- Solar + storage project 20250922002, Saluda CountySolar + storage · 74.9 MW · in study
- Solar + storage project 218, Saluda CountySolar + storage · 150 MW · withdrawn
- Solar project 142, Saluda CountySolar · 125 MW · withdrawn
- Solar project 255, Saluda CountySolar · 75.0 MW · withdrawn
- Solar project 265, Saluda CountySolar · 75.0 MW · withdrawn
- Solar project 20230829016, Saluda CountySolar · 75.0 MW · withdrawn
- Solar project 20230727002, Saluda CountySolar · 74.9 MW · withdrawn
- Solar project 20230815001, Saluda CountySolar · 74.9 MW · withdrawn
- Battery storage project 20230728001, Saluda CountyBattery storage · 74.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem