United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 103

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 103 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Willow Brook Road Solar II
Solar
1.0 MWWithdrawn / abandoned Monmouth, NJPJM Jan 2019target 2022
Hurley Solar Farm
Solar
1.0 MWWithdrawn / abandoned Monmouth, NJPJM Jul 2010target 2014
Garboski I Solar Farm
Solar
1.0 MWWithdrawn / abandoned Hunterdon, NJPJM Oct 2010target 2014
Battery storage project AC1-224, Talbot County
Battery storage
1.0 MWWithdrawn / abandoned Talbot, MDPJM Oct 2016target 2017
0
Battery storage
1.0 MWWithdrawn / abandoned Dupage, ILPJM Aug 20172018
Solar project W1-071, Salem County
Solar
1.0 MWWithdrawn / abandoned Salem, NJPJM Apr 2010target 2010
Solar project AE1-043, Gloucester County
Solar
1.0 MWWithdrawn / abandoned Gloucester, NJPJM Jul 2018target 2018
Battery storage project AE2-063, Will County
Battery storage
1.0 MWWithdrawn / abandoned Will, ILPJM Feb 2019target 2019
Battery storage project AB2-017, Atlantic County
Battery storage
1.0 MWWithdrawn / abandoned Atlantic, NJPJM Jan 2016
Battery storage project AB1-177, Atlantic County
Battery storage
1.0 MWWithdrawn / abandoned Atlantic, NJPJM Oct 2015target 2016
Battery storage project AC1-124, Guernsey County
Battery storage
1.0 MWWithdrawn / abandoned Guernsey, OHPJM Oct 2016target 2017
Battery storage project AE1-048, Queen Anne's County
Battery storage
1.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jul 2018
Solar project AH1-029, Cook County
Solar
1.0 MWWithdrawn / abandoned Cook, ILPJM Jun 2021target 2021
Battery storage project AC1-125, Guernsey County
Battery storage
1.0 MWWithdrawn / abandoned Guernsey, OHPJM Oct 2016target 2017
Solar project AE2-163, Essex County
Solar
1.0 MWWithdrawn / abandoned Essex, NJPJM Mar 2019target 2020
Solar project X2-074, Camden County
Solar
1.0 MWWithdrawn / abandoned Camden, NJPJM Jul 2011target 2012
Other project N44, Kent County
Other
1.0 MWWithdrawn / abandoned Kent, DEPJM Jan 2005target 2005
Solar project AH1-030, Cook County
Solar
1.0 MWWithdrawn / abandoned Cook, ILPJM Jun 2021target 2022
Solar project AG2-421, Cumberland County
Solar
1.0 MWWithdrawn / abandoned Cumberland, NJPJM Mar 2021target 2022
Levittown SP
Solar
1.0 MWWithdrawn / abandoned Burlington, NJPJM Apr 2010target 2011
National Harbor – Battery Storage
Battery storage
1.0 MWWithdrawn / abandoned Prince George's, MDPJM Sep 2020target 2024
Solar project X3-026, Atlantic County
Solar
1.0 MWWithdrawn / abandoned Atlantic, NJPJM Aug 2011target 2012
AES Energy Storage Unit
Battery storage
1.0 MWWithdrawn / abandoned Montgomery, PAPJM Aug 20082008
Solar project AG2-154, Northumberland County
Solar
1.0 MWWithdrawn / abandoned Northumberland, PAPJM Feb 2021target 2022
4179 Suitland Road
Solar
0.9 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2022
Other project Z2-020, Summit County
Other
0.9 MWWithdrawn / abandoned Summit, OHPJM Feb 2014target 2015
Gas project AB1-094, Cape May County
Gas
0.9 MWWithdrawn / abandoned Cape May, NJPJM Oct 2015target 2015
Lake Nelson 13 kV Solar
Solar
0.9 MWWithdrawn / abandoned Middlesex, NJPJM Jul 2016target 2018
Gas project AB1-093, Bergen County
Gas
0.9 MWWithdrawn / abandoned Bergen, NJPJM Oct 2015target 2015
Dovetail Biogas Facility
Other
0.9 MWWithdrawn / abandoned Greene, OHPJM Feb 2014target 2015
UD Motor Pool
Battery storage
0.8 MWWithdrawn / abandoned New Castle, DEPJM Feb 2018target 2022
Battery storage project AB1-120, Montgomery County
Battery storage
0.8 MWWithdrawn / abandoned Montgomery, PAPJM Oct 2015target 2016
State Route 57 Solar
Solar
0.8 MWWithdrawn / abandoned Warren, NJPJM Dec 2018target 2021
Morgantown LF
Other
0.8 MWWithdrawn / abandoned Berks, PAPJM Sep 2003target 2009
Solar project W1-104, Centre County
Solar
0.7 MWWithdrawn / abandoned Centre, PAPJM Apr 2010target 2011
Gas project AB1-118, Mercer County
Gas
0.7 MWWithdrawn / abandoned Mercer, NJPJM Oct 2015target 2016
Turnpike SP
Solar
0.6 MWWithdrawn / abandoned Hudson, NJPJM Sep 2009target 2010
Gas project AB1-034, Ocean County
Gas
0.6 MWWithdrawn / abandoned Ocean, NJPJM Aug 2015target 2015
Solar project W3-109, Cumberland County
Solar
0.6 MWWithdrawn / abandoned Cumberland, NJPJM Oct 2010target 2011
Battery storage project Y2-003
Battery storage
0.6 MWWithdrawn / abandoned ILPJM May 2012target 2014
Solar project AE1-014, Prince George's County
Solar
0.5 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2019
Hillside Battery
Battery storage
0.5 MWWithdrawn / abandoned Union, NJPJM Aug 2016target 2017
Battery storage project AB1-012, Warren County
Battery storage
0.5 MWWithdrawn / abandoned Warren, NJPJM May 2015target 2015
Solar project Y2-075, Frederick County
Solar
0.5 MWWithdrawn / abandoned Frederick, MDPJM Oct 2012target 2013
Battery storage project AB1-011, Prince George's County
Battery storage
0.5 MWWithdrawn / abandoned Prince George's, MDPJM May 2015target 2015
Montgomery Recycling
Other
0.5 MWWithdrawn / abandoned Essex, NJPJM Apr 2011target 2012
1724 64th Street
Solar
0.5 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2022
Gas project AB2-046, Washington County
Gas
0.5 MWWithdrawn / abandoned Washington, PAPJM Feb 2016target 2016
Battery storage project AB1-010, Hunterdon County
Battery storage
0.5 MWWithdrawn / abandoned Hunterdon, NJPJM May 2015target 2015
Farmingdale Solar
Solar
0.5 MWWithdrawn / abandoned Monmouth, NJPJM Jun 2009target 2011
Page 103 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)