United States βΊ Grid βΊ Interconnection queues βΊ Ohio
OTHER Β· PJMDovetail Biogas Facility
Dovetail Biogas Facility is a 0.9 MW other request withdrawn in the PJM interconnection queue, in Greene County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2014 (completed)
- Withdrawn / abandonedJul 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Z2-019
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Fairborn 12.47kV
- Location
- Greene County, Ohio
- Technology
- Other: 0.9 MW
- Total requested
- 0.9 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 7 February 2014
- Proposed online date
- June 2015
- Withdrawn
- July 2015
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Kingwood SolarSolar Β· 175 MW Β· agreement signed
- Solar + storage project AH2-093, Greene CountySolar + storage Β· 32.0 MW Β· in study
- Dovetail Biogas FacilityOther Β· 0.9 MW Β· built
- Other project G071, Greene CountyOther Β· 41.0 MW Β· withdrawn
- Solar project AG1-231, Greene CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AH2-029, Greene CountySolar Β· 18.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem