OTHER · PJMDovetail Biogas Facility
Dovetail Biogas Facility is a 0.9 MW other request built and operating in the PJM interconnection queue, in Greene County, Ohio, connecting to ATSI.
Request details
- Queue ID
- AB1-095
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Rona 12kV
- Location
- Greene County, Ohio
- Technology
- Other: 0.9 MW
- Total requested
- 0.9 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 6 October 2015
- Proposed online date
- December 2016
- Came online
- September 2016
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Kingwood SolarSolar · 175 MW · agreement signed
- Solar + storage project AH2-093, Greene CountySolar + storage · 32.0 MW · in study
- Other project G071, Greene CountyOther · 41.0 MW · withdrawn
- Solar project AG1-231, Greene CountySolar · 20.0 MW · withdrawn
- Solar project AH2-029, Greene CountySolar · 18.0 MW · withdrawn
- Dovetail Biogas FacilityOther · 0.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem