United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

Willow Brook Road Solar II

Willow Brook Road Solar II is a 1.0 MW solar request withdrawn in the PJM interconnection queue, in Monmouth County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2019 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE2-057
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Jerseyville 12.47 kV Solar
Location
Monmouth County, New Jersey
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
31 January 2019
Proposed online date
May 2022
Withdrawn
March 2021

Location

Marker shows the centre of Monmouth County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Monmouth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem