United States βΊ Grid βΊ Interconnection queues βΊ Ohio
BATTERY STORAGE Β· PJMBattery storage project AC1-124, Guernsey County
Battery storage project AC1-124, Guernsey County is a 1.0 MW battery storage request withdrawn in the PJM interconnection queue, in Guernsey County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2016 (completed)
- Withdrawn / abandonedJul 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC1-124
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Harryette 12kV
- Location
- Guernsey County, Ohio
- Technology
- Battery: 1.0 MW
- Total requested
- 1.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 27 October 2016
- Proposed online date
- October 2017
- Withdrawn
- July 2017
Location
Marker shows the centre of Guernsey County; the queue data does not give exact sites.
Other requests in Guernsey County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem