SOLAR Β· PJM

Solar project AG2-154, Northumberland County

Solar project AG2-154, Northumberland County is a 1.0 MW solar request withdrawn in the PJM interconnection queue, in Northumberland County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-154
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Danville 12 kV
Location
Northumberland County, Pennsylvania
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
25 February 2021
Proposed online date
June 2022
Withdrawn
December 2024

Location

Marker shows the centre of Northumberland County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Northumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem