Queue requests in study in the USA — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 10 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project 25-00406, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2029
Solar + storage project G0841, Lake County
Solar + storage
600 MWIn study Lake, ORWest Feb 2023target 2028
Gas project 25-00422, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Solar + storage project Company 224, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Aug 2022target 2030
Geothermal project 25-00409, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2033
Battery storage project G0808, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Solar project G0673, Crook County
Solar
600 MWIn study Crook, ORWest Mar 2021target 2028
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Gas project T2-017, Converse County
Gas · PacifiCorp
600 MWIn study Converse, WYWest Aug 2025target 2029
Capoterra
Solar
598 MWPaused / redesign Milam, TXERCOT Jun 2022
Soleil Cantil
Solar + storage
597 MWIn study Kern, CACAISO Apr 2021target 2033
Brittlebush BESS
Battery storage
597 MWPaused / redesign Henderson, TXERCOT Jun 2022
Brittlebush Solar
Solar
594 MWPaused / redesign Henderson, TXERCOT Jun 2022
Solar + storage project Q80, Kern County
Solar + storage
590 MWIn study Kern, CAWest Apr 2021target 2024
Solar + storage project Q387, Navajo County
Solar + storage
588 MWIn study Navajo, AZWest Mar 2021target 2025
Jenna Eco-Electric Solar
Solar · Clean Energy Holdings, LLC
576 MWIn study Fisher, TXERCOT May 2024target 2028
Sienna 3
Solar + storage
576 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Solar + storage project Q53, Millard County
Solar + storage · Intermountain Power Agency
570 MWIn study Millard, UTWest Jul 2016target 2019
Gas project 25-00430, Storey County
Gas
570 MWIn study Storey, NVWest Jul 2025target 2030
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)
Gas · Rayburn Energy Station LLC
570 MWIn study Grayson, TXERCOT Jan 2025target 2028
Chesterfield CT Units 1 and 2
Gas · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Solar + storage project Q2406, Maricopa County
Solar + storage
565 MWIn study Maricopa, AZWest Feb 2024target 2029
Soledad Solar
Solar
562 MWIn study Kern, CACAISO Apr 2023target 2028
Other project 110, Garfield County
Other
560 MWIn study Garfield, WAWest Jan 2021target 2025
Solar + storage project G0826, Klamath County
Solar + storage
560 MWIn study Klamath, ORWest Nov 2022target 2027
Solar + storage project J3075, Sullivan County
Solar + storage
560 MWIn study Sullivan, INMISO Sep 2022target 2025
Domestic Chicken
Solar
559 MWIn study Maricopa, AZCAISO Apr 2023target 2029
East Wonder
Solar + storage
556 MWIn study Kern, CACAISO Apr 2023target 2029
Rio Vista Solar
Solar + storage · Rio Vista Solar, LLC
554 MWIn study Pecos, TXERCOT Jun 2025target 2028
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Solar project J2478, Craighead County
Solar
550 MWIn study Craighead, ARMISO Sep 2022target 2026
Solar + storage project Company LW, Mineral County
Solar + storage
550 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Surplus; Big Bend
Wind + storage
550 MWIn study Cottonwood, MNMISO Jul 2024target 2027
Battery storage project Company MV, White Pine County
Battery storage
550 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project 20, Sacramento County
Solar + storage
550 MWIn study Sacramento, CAWest Jul 2022target 2029
Other project 2024-G4, Mohave County
Other
550 MWIn study Mohave, AZWest Apr 2024target 2027
Solar + storage project Q85, Juab County
Solar + storage · Intermountain Power Agency
550 MWIn study Juab, UTWest Oct 2021target 2025
Solar + storage project G0989, Gilliam County
Solar + storage
550 MWIn study Gilliam, ORWest Nov 2023target 2026
Miller Bend Energy BESS
Solar + storage · Miller Bend Energy
548 MWIn study Young, TXERCOT Dec 2025target 2029
Gas project GEN-2024-021, Lancaster County
Gas
540 MWIn study Lancaster, NESPP Oct 2024target 2030
Solar project J4102, Cass County
Solar
539 MWIn study Cass, MIMISO Oct 2025target 2029
Gas project 4, Osceola County
Gas · Orlando Utilities Commission
537 MWIn study Osceola, FLSoutheast Apr 1999
Other project Q591, Maricopa County
Other
535 MWIn study Maricopa, AZWest May 2025target 2030
Miller Bend Energy Solar
Solar + storage · Miller Bend Energy
532 MWIn study Young, TXERCOT Dec 2025target 2029
Merom Station
Gas · Hallador Power
530 MWIn study Sullivan, INMISO Nov 2025target 2028
Gas project 25RSC-011, Morgan County
Gas
528 MWIn study Morgan, ALSoutheast Aug 2025target 2031
Sagebrush Energy Storage
Battery storage
528 MWIn study Kern, CACAISO Apr 2021target 2033
Mojo Solar
Solar + storage · Power Synergy
528 MWIn study Wilson, TXERCOT Mar 2025target 2028
Mitchell BESS
Battery storage · NIPSCO
527 MWIn study Lake, INMISO Aug 2025target 2028
Gas project 760, Elmore County
Gas
526 MWIn study Elmore, IDWest Apr 2025target 2030
Page 10 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)