SOLAR Β· OPERATIONAL

Long Ash Lane Solar Park

Long Ash Lane Solar Park is a 5 MW solar farm in South West England, operated by Atmosclear. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningSep 2015 (completed)
  2. ConsentedJan 2016 (completed)
  3. ConstructionSep 2016 (completed)
  4. OperatingFeb 2017 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
5 MW
Status
Operational
Technology
Solar Β· PV
Operator
Atmosclear
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
DT2 9PW
Coordinates
50.8211, -2.5560

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Long Ash Lane Solar Park compares

252nd of 662largest solar farms in the UK register
72nd of 192in South West
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Atmosclear

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Southern Counties Shooting Ground Phase 2
Developer / operator
British Solar Renewables
Planning authority
Dorset
Planning reference
WD/D/15/001862
Application submitted
8 September 2015
Permission granted
8 January 2016
Construction started
20 September 2016
Began operating
2 February 2017
Capacity in planning record
5 MW
Address
Southern Counties Leisure, Long Ash Lane, Wardon Hill, Dorset
REPD reference
5891

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.