Caswell
Caswell is a 5.91 MW solar farm in South West England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 5.91 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- BA22 9RH
- Coordinates
- 50.8815, -2.6050
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Caswell compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5.91 MW station would generate roughly 5.2 GWh of electricity in a year, similar to the annual use of about 1,920 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Octopus InvestmentsNearby generating sites
- Long Ash Lane Solar Park Β· 5 MW solar farm7.5 km
- North Perrott Fruit Farm Β· 0.82 MW solar farm11.1 km
- Chilton Cantelo Solar park Β· 5 MW solar farm12.6 km
- Southfield Β· 9.76 MW solar farm14.7 km
- Milborne Port Β· 3.29 MW solar farm14.9 km
- Bourne Park Β· 0.25 MW solar farm18.7 km
- Bourne Park 2 Β· 2.4 MW solar farm18.9 km
- Hurcott Β· 10 MW solar farm19.3 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Caswell Farm Solar Park
- Developer / operator
- Juwi Renewable Energies
- Planning authority
- Dorset
- Planning reference
- 1/D/13/000242
- Application submitted
- 8 March 2013
- Permission granted
- 13 December 2013
- Construction started
- 23 January 2016
- Began operating
- 23 March 2016
- Capacity in planning record
- 6.7 MW
- Address
- Caswell Farm, Common Lane, Ryme Intrinseca, Sherborne, Dorset, Dorset, DT9 6JP
- REPD reference
- 1898
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.