Chilton Cantelo Solar park
Chilton Cantelo Solar park is a 5 MW solar farm in South West England, operated by Wise Energy Limited. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Wise Energy Limited
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- BA22 8BQ
- Coordinates
- 50.9945, -2.6027
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Chilton Cantelo Solar park compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Wise Energy LimitedNearby generating sites
- Southfield Β· 9.76 MW solar farm2.3 km
- Manor Farm Β· 4.87 MW solar farm8.8 km
- Milborne Port Β· 3.29 MW solar farm10.6 km
- Copley Wood (Renewables (SW)) Β· 1.5 MW solar farm12.0 km
- Caswell Β· 5.91 MW solar farm12.6 km
- Somerton Door Β· 8.7 MW solar farm13.5 km
- Sutor Β· 4.99 MW solar farm15.6 km
- North Perrott Fruit Farm Β· 0.82 MW solar farm16.3 km
Also operated by Wise Energy Limited
Wise Energy Limited operates 9 sites in the register. Largest first:
- Hook Valley Solar Park Β· solar farm15.3 MW
- Burcroft Solar Parks Β· solar farm12.7 MW
- Whitley (Ashcott Farm) Solar Park Β· solar farm7.57 MW
- Blenches Mill Solar Park Β· solar farm6.08 MW
- Raglington Farm Solar Park Β· solar farm5.73 MW
- Crossways Solar Park Β· solar farm5 MW
- Wyld Meadow Farm Solar Park Β· solar farm4.84 MW
- Knockworthy Farm Solar Park Β· solar farm4.65 MW
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Chilton Cantelo Solar Farm
- Developer / operator
- NextEnery Solar Fund (NESF)
- Planning authority
- Somerset
- Planning reference
- 12/01055/FUL
- Application submitted
- 20 March 2012
- Permission granted
- 11 July 2012
- Began operating
- 28 February 2013
- Capacity in planning record
- 5 MW
- Address
- The Cypress House Road, Chilton Cantelo, Yeovil, Somerset, BA22 8BQ, Somerset
- REPD reference
- 1344
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.