Higher Pirzwell is a 1.2 MW solar farm in South West England, operated by Atmosclear. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 1.2 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Atmosclear
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- EX15 2AH
- Coordinates
- 50.8745, -3.3154
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Higher Pirzwell compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1.2 MW station would generate roughly 1.1 GWh of electricity in a year, similar to the annual use of about 390 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by AtmosclearNearby generating sites
- Nether Mill Β· 3.77 MW solar farm6.3 km
- Dunkeswell Β· 2.8 MW solar farm6.3 km
- Kia-Ora Farm Β· 1.8 MW solar farm6.9 km
- Barton Β· 1.2 MW solar farm8.0 km
- RedHill Farm Β· 4.8 MW solar farm9.0 km
- Francis Court Β· 4.22 MW solar farm13.5 km
- Burcroft Solar Parks Β· 12.7 MW solar farm13.7 km
- Trickey Warren Β· 4.63 MW solar farm13.7 km
Also operated by Atmosclear
Atmosclear operates 9 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Higher Pirzwell Solar Farm
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Mid Devon
- Planning reference
- 12/00373/MFUL
- Application submitted
- 14 March 2012
- Permission granted
- 21 May 2012
- Construction started
- 25 June 2012
- Began operating
- 26 July 2012
- Capacity in planning record
- 1.2 MW
- Address
- Higher Pirzwell, Kentisbeare, Cullompton, Devon, Devon, EX15 2AH
- REPD reference
- 1617
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.