Kia-Ora Farm

Kia-Ora Farm is a 1.8 MW solar farm in South West England, operated by Atmosclear. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningSep 2012 (completed)
  2. ConsentedNov 2012 (completed)
  3. ConstructionJan 2013 (completed)
  4. OperatingMar 2013 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
1.8 MW
Status
Operational
Technology
Solar Β· PV
Operator
Atmosclear
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
EX15 1PZ
Coordinates
50.8545, -3.4082

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Kia-Ora Farm compares

620th of 662largest solar farms in the UK register
169th of 192in South West
0.03%of listed UK solar farms capacity
β‰ˆ 1.6 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1.8 MW station would generate roughly 1.6 GWh of electricity in a year, similar to the annual use of about 580 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Atmosclear

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Kia Ora Farm
Developer / operator
Lightsource Renewable Energy
Planning authority
Mid Devon
Planning reference
12/01350/MFUL
Application submitted
19 September 2012
Permission granted
30 November 2012
Construction started
30 January 2013
Began operating
21 March 2013
Capacity in planning record
1.8 MW
Address
Knowle Lane, Cullompton, Devon, Devon, EX15 1PZ
REPD reference
1441

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.