Tillhouse
Tillhouse is a 10.5 MW solar farm in South West England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 10.5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- EX5 3BG
- Coordinates
- 50.7599, -3.4048
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Tillhouse compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 10.5 MW station would generate roughly 9.2 GWh of electricity in a year, similar to the annual use of about 3,410 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Octopus InvestmentsNearby generating sites
- Burcroft Solar Parks Β· 12.7 MW solar farm1.1 km
- Strete Β· 4.85 MW solar farm3.6 km
- Francis Court Β· 4.22 MW solar farm4.4 km
- Exeter Β· 50 MW open-cycle gas power station10.3 km
- Kia-Ora Farm Β· 1.8 MW solar farm10.5 km
- Coombe Β· 7.28 MW solar farm11.9 km
- Bystock Farm Β· 4.05 MW solar farm12.2 km
- Higher Pirzwell Β· 1.2 MW solar farm14.2 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Crannaford Solar Farm
- Developer / operator
- MS Power Projects
- Planning authority
- East Devon
- Planning reference
- 13/0430/MFUL
- Application submitted
- 28 February 2013
- Permission granted
- 5 September 2013
- Construction started
- 20 January 2014
- Began operating
- 31 March 2014
- Capacity in planning record
- 12.5 MW
- Address
- Land North East Of Crannaford House Broadclyst, Devon
- REPD reference
- 1984
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.