πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Stables Farm

Stables Farm is a 1 MW solar farm in South East England, operated by Atmosclear. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South East
  • England
Project stageOperating
  1. PlanningMar 2012 (completed)
  2. ConsentedJun 2012 (completed)
  3. ConstructionJul 2012 (completed)
  4. OperatingAug 2012 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
1 MW
Status
Operational
Technology
Solar Β· PV
Operator
Atmosclear
Region
South East
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PO30 4NH
Coordinates
50.6971, -1.4220

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Stables Farm compares

646th of 662largest solar farms in the UK register
104th of 105in South East
0.02%of listed UK solar farms capacity
β‰ˆ 0.9 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 1 MW station would generate roughly 0.9 GWh of electricity in a year, similar to the annual use of about 320 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South East All run by Atmosclear

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Lightsource Renewable Energy
Planning authority
Isle of Wight
Planning reference
P/00353/12
Application submitted
13 March 2012
Permission granted
12 June 2012
Construction started
9 July 2012
Began operating
7 August 2012
Capacity in planning record
1.5 MW
Address
Warlands Lane Shalfleet Newport Isle Of Wight PO30 4NH, Isle of Wight
REPD reference
1421

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.