Fawley (Langley)
Fawley (Langley) is a 5 MW solar farm in South East England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SO45 1AB
- Coordinates
- 50.8051, -1.3603
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Fawley (Langley) compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Lightsource BPNearby generating sites
- Mopley/Cadland Β· 3.02 MW solar farm0.5 km
- Hythe Β· 53 MW open-cycle gas power station5.2 km
- Cowes Β· 140 MW oil-fired power station8.0 km
- Netley Β· 5 MW solar farm8.3 km
- Chawton Β· 3.65 MW solar farm8.8 km
- Marchwood Power Β· 898 MW CCGT gas power station10.1 km
- Fareham Β· 20.5 MW solar farm11.9 km
- Tavells Β· 5.41 MW solar farm12.1 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- The Manor of Cadland Estate
- Developer / operator
- The Manor of Cadland Estate
- Planning authority
- New Forest
- Planning reference
- 11/96086
- Application submitted
- 21 January 2011
- Permission granted
- 17 May 2011
- Construction started
- 22 May 2012
- Began operating
- 23 July 2012
- Capacity in planning record
- 5 MW
- Address
- Whitefield Farm, Langley, Hampshire
- REPD reference
- 1562
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.