Mopley/Cadland
Mopley/Cadland is a 3.02 MW solar farm in South East England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 3.02 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SO45 1YH
- Coordinates
- 50.8064, -1.3673
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Mopley/Cadland compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 3.02 MW station would generate roughly 2.6 GWh of electricity in a year, similar to the annual use of about 980 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Octopus InvestmentsNearby generating sites
- Fawley (Langley) Β· 5 MW solar farm0.5 km
- Hythe Β· 53 MW open-cycle gas power station5.0 km
- Netley Β· 5 MW solar farm8.3 km
- Cowes Β· 140 MW oil-fired power station8.3 km
- Chawton Β· 3.65 MW solar farm9.2 km
- Marchwood Power Β· 898 MW CCGT gas power station9.6 km
- Tavells Β· 5.41 MW solar farm11.7 km
- Marchwood Power Station Β· 840 MW power station12.3 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- The Manor of Cadland Estate - extension
- Developer / operator
- Manor of Cadland
- Planning authority
- New Forest
- Planning reference
- 13/98465
- Application submitted
- 30 April 2013
- Permission granted
- 18 July 2013
- Began operating
- 7 February 2014
- Capacity in planning record
- 3 MW
- Address
- NEWHOUSE FIELD, WHITEFIELD FARM, LANGLEY, HAMPSHIRE, SO45 1YH, Hampshire
- REPD reference
- 1669
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.