NESO TEC REGISTER · GREAT BRITAINGrid connection projects in the connection queue on the National Grid (England & Wales) network
Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.
Map
Voltage400 kV275 kV132 kVHVDCNew HVAC
ProjectsPlanningConsentedConstructionBuiltMajor project with its own page
Projects
| Project | Capacity | Stage |
|---|---|---|
| SPR CS1 Offshore wind · Scottish Power Renewables (UK) Limited |
1.0 GW | Scoping |
| Stoke Bardolph Solar + storage · Stoke Bardolph 10 Renewables Limited |
1.0 GW | Scoping |
| West Haddon Solar · West Haddon 10 Renewables Limited |
1.0 GW | Scoping |
| West Weybridge Solar + storage · West Weybridge 10 Renewables Limited |
1.0 GW | Scoping |
| Wymondley Farm Solar + storage · Wymondley 10 Renewables Ltd |
1.0 GW | Scoping |
| Wymondley High Impact Green Energy Hub (HIGEH) 1 Solar + storage · Telis Energy UK Limited |
1.0 GW | Scoping |
| The Superconnection Interconnector · Asc Energy plc |
1.0 GW | Scoping |
| Bradford Solar Farm Solar · SolarFour Ltd |
960 MW | Scoping |
| Scira-Dudgeon Extension Offshore wind · Sheringham Shoal And Dudgeon Extensions Projco Limited |
950 MW | Scoping |
| Norwich Main BESS Solar + storage · Tasway Energy Park Limited |
950 MW | Scoping |
| Trawsfynydd B Cwmni Egino Nuclear · Cwmni Egino |
940 MW | Scoping |
| Lacey's Farm BESS Battery storage · Bluestone Energy Ltd |
924 MW | Scoping |
| Protos Power Station Gas · Keadby Generation Limited |
910 MW | Scoping |
| Stallingborough Carbon Capture Ccgt Gas · RWE Generation UK Plc |
906 MW | Scoping |
| Elmya Gissing BESS & PV Solar + storage · Rpc Elmya Carnation Gissing Limited |
900 MW | Scoping |
| Keadby North Power Station Gas · Keadby Generation Limited |
892 MW | Awaiting Consents |
| East Anglia One North Offshore wind · East Anglia One North Limited |
880 MW | Awaiting Consents |
| East Anglia Two Offshore wind · East Anglia Two Limited |
880 MW | Awaiting Consents |
| East Anglia One North Offshore wind · East Anglia One North Limited |
860 MW | Awaiting Consents |
| East Anglia Two Offshore wind · East Anglia Two Limited |
860 MW | Awaiting Consents |
| Norfolk001 Solar + storage · Epl Newco1 Limited |
860 MW | Scoping |
| Bradenham - Thetford (Necton) GEC (Ethos Green) Solar + storage · Necton Green Energy Centre Ltd |
850 MW | Scoping |
| Buntington GEC Solar + storage · Buntington Green Energy Centre Ltd |
850 MW | Awaiting Consents |
| Elmya Kilworth BESS & PV Solar + storage · Rpc Elmya Carnation Kilworth Limited |
850 MW | Scoping |
| Elmya Ryston BESS & PV Solar + storage · Elmya Energy UK 13 Limited |
850 MW | Scoping |
| Hockliffe GEC (Ethos Green) Solar + storage · Hockliffe Green Energy Centre Ltd |
850 MW | Scoping |
| Botley West - Cote Solar Power Station Solar · Solarfive Ltd |
840 MW | Awaiting Consents |
| Woburn Solar Farm Solar · SolarThree Ltd |
840 MW | Scoping |
| Grantham Solar Farm - RSL Solar + storage · South Grantham Energy Centre Limited |
810 MW | Scoping |
| Botley GEC (Ethos Green) Solar + storage · Botley Green Energy Centre Ltd |
800 MW | Awaiting Consents |
| Cliff Hill Energy Farm Solar + storage · Renewable Energy Systems Limited |
800 MW | Scoping |
| East Lincolnshire Solar Solar + storage · Statkraft UK Ltd |
800 MW | Scoping |
| Elmya Foxdale BESS Battery storage · Rpc Elmya Carnation Foxdale Limited |
800 MW | Scoping |
| Hill Street Solar PV/BESS Station Solar + storage · Hill Street Shelfco 1 Limited |
800 MW | Scoping |
| Melksham BESS & PV Solar + storage · Elements Green Limited |
800 MW | Scoping |
| Monk Fryston Energy Park Solar + storage · Elements Green Development Ltd |
800 MW | Scoping |
| NatPower Hartlepool Green Energy Park Battery storage · Np Spv 34 Limited |
800 MW | Scoping |
| Scarning Solar + storage · Connectid 3 Limited |
800 MW | Awaiting Consents |
| Springwell Solar + storage · Springwell Energyfarm Limited |
800 MW | Scoping |
| Stockhills Farm Solar + storage · Bsr Applications Limited |
800 MW | Scoping |
| Sweet Briar Energy Park Solar + storage · Sweet Briar 2 Energy Park Limited |
800 MW | Scoping |
| Tween Bridge Solar Park Solar + storage · RWE Renewables UK Solar and Storage Limited |
800 MW | Scoping |
| New Marton Solar Farm - PVDP Solar + storage · SolarFour Ltd |
780 MW | Scoping |
| Didcot BESS 1 Battery storage · Downing Renewable Developments LLP |
750 MW | Scoping |
| East Pit Solar + storage · Cs UK Holdings III Limited |
750 MW | Scoping |
| FCC Thurcroft BESS Battery storage · Downing Renewable Developments LLP |
750 MW | Scoping |
| Meridian Solar Farm Solar + storage · Meridian Solar Farm Limited |
750 MW | Scoping |
| Old Flatts Farm Solar + storage · Net Zero One Ltd |
750 MW | Scoping |
| Mares Interconnector · Maresconnect Limited |
750 MW | Awaiting Consents |
| One Earth Solar Farm Solar + storage · One Earth Solar Farm Limited |
740 MW | Awaiting Consents |
Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.