🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown2,255782.1 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

2,255 projects · page 10 of 46
ProjectCapacityStageConnection siteFrom
Earl Shilton BESS
Battery storage · Exagen Normanton Energy Reserve Limited
500 MWScoping Earl Shilton 275kV
National Grid (England & Wales)
Oct 2029
East Claydon Storage
Battery storage · East Claydon Storage Limited
500 MWScoping East Claydon 400kV Substation
National Grid (England & Wales)
Oct 2026
Eaton Socon Solar
Solar + storage · Brockwell Storage & Solar Limited
500 MWScoping Eaton Socon 400kV Substation
National Grid (England & Wales)
Oct 2028
Eccles BESS
Battery storage · Eccles Energy Centre Limited
500 MWUnder Construction/Commissioning Eccles 400kV Substation
SP Transmission (south Scotland)
Apr 2026
Elstree BESS NP
Battery storage · Elstree Flexpower Ltd
500 MWScoping Elstree B 275Kv Substation
National Grid (England & Wales)
Oct 2037
Enderby Solar & BESS
Solar + storage · Greentech Projects Holding UK Limited
500 MWScoping Derbyshire Connection Node H 400kV Substation
National Grid (England & Wales)
Oct 2037
Ewerby
Solar + storage · Leoda Solar Farm Limited
500 MWScoping Navenby 400kV Substation
National Grid (England & Wales)
Oct 2035
Feckenham
Solar + storage · Igp Solar 14 Limited
500 MWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Jul 2029
Feckenham Energy Park
Battery storage · Green Energy Mab Ltd
500 MWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Oct 2033
Greater Gabbard Offshore Wind Farm
Offshore wind · Greater Gabbard Offshore Winds Limited
500 MWBuilt Gabbard 33/132kV Offshore Substation
Offshore transmission owner
Green Hydrogen Solar Farm
Solar + storage · Green Hydrogen Solar Farm Limited
500 MWScoping Sealand 400kV Substation
National Grid (England & Wales)
Nov 2037
Greengage Farm
Solar + storage · Renewable Energy Systems Limited
500 MWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2034
Grendon Solar & BESS
Solar + storage · Green Hill Solar Farm Limited
500 MWScoping Grendon 400kV Substation
National Grid (England & Wales)
Jul 2029
Greta III
Solar + storage · Tagenergy Development UK Limited
500 MWConsents Approved Drakelow 400kV Substation
National Grid (England & Wales)
Oct 2029
Greta IV (b)
Solar + storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Greta IV (c)
Battery storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Greta IV (d)
Battery storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Grimsby BESS
Battery storage · Shama BESS Limited
500 MWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
Apr 2035
Hagshaw LDES
Battery storage · Hagshaw Ldes Ltd
500 MWScoping Redshaw 132kV Substation.
SP Transmission (south Scotland)
Oct 2036
Hawkhill BESS
Battery storage · GPC Project 12 Ltd
500 MWScoping Kincardine North 400kV Substation
SP Transmission (south Scotland)
Oct 2031
High Marnham BESS
Battery storage · Jg Pears Grid Connection Limited
500 MWScoping High Marnham 400kV Substation
National Grid (England & Wales)
Oct 2034
Holdsworth Road
Battery storage · Mas 002 Limited
500 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
Oct 2036
Killingholme Energy Park
Solar + storage · Exagen Group Limited
500 MWScoping South Humber Connection Node A 400kV
National Grid (England & Wales)
Oct 2035
Kilmarnock South Battery Storage
Battery storage · Kilmarnock Energy Centre Limited
500 MWConsents Approved Kilmarnock South 400kV Substation
SP Transmission (south Scotland)
Apr 2027
Kingsnorth BESS NP
Battery storage · Noriker Power Ltd
500 MWScoping Kingsnorth 400kV Substation
National Grid (England & Wales)
Dec 2030
Kinoulton Solar & BESS
Solar + storage · Greentech Invest UK (16) Limited
500 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Lanarkshire BESS
Battery storage · Carlton Power Limited
500 MWAwaiting Consents Strathaven 400/275kV
SP Transmission (south Scotland)
Apr 2027
Lincolnshire Energy Park
Solar + storage · Wind 2 Limited
500 MWScoping South Humber Connection Node A 400kV
National Grid (England & Wales)
Oct 2039
Long Buckby Solar/BESS
Solar + storage · Greentech Invest UK (17) Limited
500 MWScoping Derbyshire Connection Node I 400kV Substation
National Grid (England & Wales)
Oct 2037
Long Stratton PV & BESS Station
Solar + storage · East Pye Solar Limited
500 MWScoping Long Stratton 400kV
National Grid (England & Wales)
Oct 2031
Longfield Solar
Solar + storage · Longfield Solar Energy Farm Limited
500 MWScoping Bulls Lodge 400kV Substation
National Grid (England & Wales)
Oct 2028
Longhaven Energy Storage Centre
Hydro and pumped storage · Hydrostor UK Ltd
500 MWScoping New North East Substation 400kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Ludgershall - Bicester Solar Farm PVDP
Solar + storage · SolarFour Ltd
500 MWScoping Chiltern Connection Node C 400kV Substation
National Grid (England & Wales)
Nov 2038
Manor Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping East Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Medway 3 Power Station
Battery storage · Medway Power Limited
500 MWScoping Kingsnorth 400kV Substation
National Grid (England & Wales)
Apr 2032
Melksham
Solar + storage · Lime Down Solar Park Limited
500 MWAwaiting Consents Melksham 400kV Substation
National Grid (England & Wales)
Jul 2030
Moffat BESS
Battery storage · Conrad Energy (Developments) II Limited
500 MWScoping Moffat 400kV Substation
SP Transmission (south Scotland)
Oct 2031
Monk Fryston
Solar + storage · Light Valley Solar Limited
500 MWScoping Monk Fryston 400kV Substation
National Grid (England & Wales)
Dec 2029
Mybster 2 Battery Storage
Battery storage · Potencia Energy (Mybster) Ltd
500 MWScoping Thurso South 400kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Nant Helen
Solar + storage · Solar Securities Limited
500 MWScoping South Wales West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
NatPower CoalBurn Green Energy Park
Battery storage · Coalburn Energy Limited
500 MWScoping NatPower Green Energy Park 400kV Substation
SP Transmission (south Scotland)
Oct 2036
NatPower Connah Quay Green Energy Park
Battery storage · Connahs Quay Energy Limited
500 MWScoping Cheshire Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
NatPower Kintore2 Green Energy Park
Battery storage · Np Spv 41 Limited
500 MWScoping Natpower Kintore 2 Green Energy Park 275Kv Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer Battery Storage
Battery storage · New Deer Energy Centre Limited
500 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer BESS Station
Battery storage · Abbotshaugh Energy Storage Limited
500 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Oxfordshire Energy Park
Solar + storage · Low Carbon Solar Park 40 Limited
500 MWScoping Chiltern Connection Node D 400kV
National Grid (England & Wales)
Oct 2037
Partridge Farm BESS
Battery storage · Apatura Battery Ltd
500 MWScoping Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2037
Penrhiwdarren Farm
Battery storage · Qair Renewables UK Limited
500 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Sep 2037
Peterhead Battery
Battery storage · Peterhead Flexpower Ltd
500 MWScoping Peterhead 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Project Number 4
Solar + storage · Greta IV Limited
500 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Page 10 of 46

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.