Gas project 3, Polk County is a 297 MW gas request built and operating in the Southeast interconnection queue, in Polk County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Mar 1999 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2000 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
3
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Intercession City Substation 230 kV
Location
Polk County, Florida
Technology
Gas: 297 MW
Total requested
297 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
1 March 1999
Came online
December 2000

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.