United States › Grid › Interconnection queues › Florida
SOLAR · SOUTHEASTSolar project 11, Polk County
Solar project 11, Polk County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Polk County, Florida, connecting to Tampa Electric Company.
Request details
- Queue ID
- 11
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tampa Electric Company
- Connection point (POI)
- Ft. Green Meter Station, Polk County, Florida
- Location
- Polk County, Florida
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Interconnection Agreement Executed
- Queue status
- Operational
- Entered queue
- 19 April 2017
- Proposed online date
- July 2018
Location
Marker shows the centre of Polk County; the queue data does not give exact sites.
Other requests in Polk County
- Gas project 333, Polk CountyGas · 84.0 MW · under construction
- Solar project 273, Polk CountySolar · 74.9 MW · under construction
- Solar project 76, Polk CountySolar · 55.0 MW · agreement signed
- Other project 70, Polk CountyOther · 48.0 MW · agreement signed
- Gas project 118, Polk CountyGas · 132 MW · in study
- Solar project 111, Polk CountySolar · 52.0 MW · in study
- Battery storage project 120, Polk CountyBattery storage · 20.0 MW · in study
- Solar project 123, Polk CountySolar · 19.5 MW · in study
- Gas project 2, Polk CountyGas · 1,701 MW · built
- Gas project 2Gas · 701 MW · built
- Gas project 135, Polk CountyGas · 637 MW · built
- Gas project 1Gas · 567 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem