๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown41171.6 GW
Active in queue71.6 GW411 requests
Agreement signed12.4 GW73 requests
Withdrawn51088.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

411 requests ยท page 1 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q468, Maricopa County
Battery storage
1,000 MWIn study Maricopa, AZWest Mar 2022target 2025
Battery storage project G0796, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Battery storage project G0778, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Aug 2022target 2027
Battery storage project G0774, Wasco County
Battery storage
650 MWIn study Wasco, ORWest Aug 2022target 2028
Battery storage project G0792, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Battery storage project G0807, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Tempesta BESS
Battery storage
600 MWPaused / redesign Kaufman, TXERCOT Jun 2022
Capoterra BESS
Battery storage
600 MWPaused / redesign Milam, TXERCOT Jun 2022
Battery storage project G0812, Lane County
Battery storage
600 MWIn study Lane, ORWest Sep 2022target 2030
Battery storage project G0808, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Brittlebush BESS
Battery storage
597 MWPaused / redesign Henderson, TXERCOT Jun 2022
Battery storage project Company MV, White Pine County
Battery storage
550 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Midnight Sun Energy Storage
Battery storage ยท Midnight Sun Energy Storage, LLC
510 MWAgreement signed Crockett, TXERCOT Dec 2022target 2028
Bayside BESS
Battery storage
508 MWPaused / redesign Victoria, TXERCOT Mar 2022
Battery storage project C2-10, Salt Lake County
Battery storage ยท Oquirrh Energy Storage, LLC
500 MWAgreement signed Salt Lake, UTWest Apr 2022target 2031
Battery storage project J2590, Huron County
Battery storage
500 MWIn study Huron, MIMISO Sep 2022target 2025
Battery storage project AH2-416, Livingston County
Battery storage
450 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project AI1-022, Huntington County
Battery storage
450 MWIn study Huntington, INPJM Apr 2022target 2026
Battery storage project AH2-333, Salem County
Battery storage
415 MWIn study Salem, NJPJM Mar 2022target 2025
Battery storage project Company 212, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Battery storage project IC-1102, Montgomery County
Battery storage
400 MWPaused / redesign Montgomery, ALSoutheast Dec 2022target 2026
Battery storage project Company 226, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Battery storage project Company 228, Clark County
Battery storage
380 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Battery storage project AH2-414, Huntington County
Battery storage
350 MWIn study Huntington, INPJM Mar 2022target 2026
Battery storage project 696, Owyhee County
Battery storage ยท KCE ID 1, LLC
330 MWAgreement signed Owyhee, IDWest Dec 2022target 2026
Elio BESS
Battery storage ยท Elio Energy LLC
317 MWAgreement signed Brazoria, TXERCOT Jul 2022target 2027
Royal River BESS
Battery storage ยท Royal River LLC
311 MWIn study Brazoria, TXERCOT Mar 2022target 2027
Red Egret BESS
Battery storage ยท Red Egret LLC
311 MWAgreement signed Galveston, TXERCOT Mar 2022target 2026
Two Forks BESS
Battery storage ยท Two Forks LLC
310 MWAgreement signed Cooke, TXERCOT Jan 2022target 2027
Blue Skies BESS
Battery storage ยท ACTX BESS Project LLC
306 MWAgreement signed Hill, TXERCOT May 2022target 2027
Furay Battery Energy Storage System
Battery storage ยท Blue Topaz 1, LLC
304 MWIn study Harris, TXERCOT Sep 2022target 2027
Great Rock BESS
Battery storage ยท Black Mountain Energy Storage II
301 MWAgreement signed Leon, TXERCOT Nov 2022target 2027
Battery storage project Company 213, Clark County
Battery storage
300 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Battery storage project J2469, Linn County
Battery storage
300 MWIn study Linn, IAMISO Sep 2022target 2027
Battery storage project J2716, Dakota County
Battery storage
300 MWIn study Dakota, MNMISO Sep 2022target 2027
Battery storage project AH2-133, City Of Chesapeake County
Battery storage
300 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Battery storage project AI1-024, Mclean County
Battery storage
300 MWIn study Mclean, ILPJM Apr 2022target 2026
Battery storage project IC-1091, Mobile County
Battery storage
300 MWPaused / redesign Mobile, ALSoutheast Nov 2022target 2027
Battery storage project 632, Owyhee County
Battery storage ยท NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Owyhee, IDWest Jan 2022target 2025
Battery storage project Q467, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Mar 2022target 2026
Battery storage project J2647, Franklin County
Battery storage
300 MWIn study Franklin, ILMISO Sep 2022target 2028
Battery storage project J2215, Lake County
Battery storage
300 MWIn study Lake, INMISO Mar 2022target 2024
Battery Storage
Battery storage
300 MWIn study Norfolk, MAISO-NE Mar 2022target 2028
Battery storage project AI1-017, Surry County
Battery storage
300 MWIn study Surry, VAPJM Apr 2022target 2026
Battery storage project AH2-334, Camden County
Battery storage
300 MWIn study Camden, NJPJM Mar 2022target 2025
Battery storage project AH2-415, Livingston County
Battery storage
300 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project GEN-2022-073, Clay County
Battery storage
300 MWIn study Clay, MOSPP Sep 2022target 2030
Battery storage project AI1-018, Spotsylvania County
Battery storage
300 MWIn study Spotsylvania, VAPJM Apr 2022target 2026
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Page 1 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)