OCTARY USA ยท INTERCONNECTION QUEUES

Gas interconnection queue in the USA (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13253.0 GW
Active in queue53.0 GW132 requests
Agreement signed12.5 GW23 requests
Withdrawn6030.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

132 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Smarr CC
Gas
2,000 MWIn study Monroe, GASoutheast Aug 2024target 2028
Gas project 628, Todd County
Gas
1,600 MWIn study Todd, KYSoutheast Jun 2024target 2030
Gas project 620, Trousdale County
Gas
1,600 MWIn study Trousdale, TNSoutheast Jun 2024target 2031
Aegle Power
Gas ยท Aegle Power LLC
1,536 MWIn study Cameron, TXERCOT Jul 2024target 2027
Gas project 958347, Person County
Gas ยท Duke Energy Progress, LLC
1,455 MWIn study Person, NCSoutheast Jun 2024
Gas project J3799, Livingston County
Gas
1,452 MWIn study Livingston, MIMISO Apr 2024target 2030
Gas project 957264, Anderson County
Gas
1,450 MWIn study Anderson, SCSoutheast Jun 2024
Sandow Lakes Energy Station
Gas ยท SL Energy Power Plant I, LLC
1,292 MWIn study Milam, TXERCOT Mar 2024target 2028
Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem
Gas
1,232 MWIn study Iberville, LAMISO May 2024target 2025
Replacement; Oak Creek Units 5-8
Gas
1,138 MWIn study Milwaukee, WIMISO Jun 2024target 2027
Bastrop Peaking Generators (TEF-Due Diligence)
Gas ยท MPH Bastrop Peakers, LLC
1,104 MWAgreement signed Bastrop, TXERCOT Feb 2024target 2027
Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2
Gas
1,040 MWIn study Vermillion, INMISO Feb 2024target 2028
EmberGreen
Gas ยท EmberGreen Energy Center
1,036 MWIn study Wharton, TXERCOT Jun 2024target 2028
Gas project IC-1254b, Heard County
Gas
1,003 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Gas project IC-1254a, Heard County
Gas
1,003 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
EmberYork
Gas ยท EmberYork Energy Center
900 MWAgreement signed Austin, TXERCOT Aug 2024target 2028
West Royal Natural Gas (TEF-Due Diligence)
Gas ยท Invenergy Energy Transition Development LLC
888 MWIn study Upton, TXERCOT Jun 2024target 2030
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff
Gas
824 MWIn study St. Louis, MOMISO May 2024target 2025
Gas project 174, Pima County
Gas
800 MWIn study Pima, AZWest Jun 2024target 2027
Gas project 618, Stewart County
Gas
800 MWIn study Stewart, TNSoutheast Jun 2024target 2027
Gas project 622, Trousdale County
Gas
800 MWIn study Trousdale, TNSoutheast Jun 2024target 2031
Flint River 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Oct 2024target 2029
Gas project J3829, Hot Spring County
Gas
770 MWIn study Hot Spring, ARMISO Apr 2024target 2028
Gas project J3874, Union County
Gas
770 MWIn study Union, ARMISO Dec 2024target 2028
Central Power Station
Gas ยท Hydra-Gen Energy Unlimited
750 MWIn study Grimes, TXERCOT Mar 2024target 2027
Gas project GEN-2024-082, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2030
Gas project GEN-2024-081, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2029
Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; Schahfer
Gas
733 MWIn study Jasper, INMISO Dec 2024target 2027
Gas project IC-1255, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2028
Gas project IC-1257, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1256, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1260, Effingham County
Gas
722 MWIn study Effingham, GASoutheast Mar 2024target 2031
Gas project IC-1264, Heard County
Gas
722 MWAgreement signed Heard, GASoutheast Mar 2024target 2029
Gas project IC-1258, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1263, Heard County
Gas
722 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Gas project IC-1259, Effingham County
Gas
722 MWAgreement signed Effingham, GASoutheast Mar 2024target 2029
Gas project J3604, Sullivan County
Gas
650 MWIn study Sullivan, INMISO Apr 2024target 2027
Gas project GEN-2024-GR5, Chouteau County
Gas
594 MWAgreement signed Chouteau, OKSPP Aug 2024target 2026
Gas project GEN-2024-021, Lancaster County
Gas
540 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project J3232, Vermillion County
Gas
500 MWIn study Vermillion, INMISO Apr 2024target 2028
Gas project GEN-2024-013, Mcclain County
Gas
496 MWIn study Mcclain, OKSPP Aug 2024target 2030
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
North Royal Thermal (TEF- Due Diligence)
Gas ยท Invenergy Energy Transition Development LLC
479 MWIn study Lamar, TXERCOT Jun 2024target 2030
Gas project J3331, Sullivan County
Gas
470 MWIn study Sullivan, INMISO Apr 2024target 2028
Gregory Power Development SLF
Gas ยท Gregory Power Partners LLC
470 MWIn study San Patricio, TXERCOT Nov 2024target 2028
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project 960889, Rowan County
Gas
455 MWIn study Rowan, NCSoutheast Jun 2024
Gas project 961188, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 961210, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 956747, Rowan County
Gas
455 MWIn study Rowan, SCSoutheast Jun 2024
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)