Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown142,780 MW
Active in queue200.1 GW826 requests
Agreement signed49.9 GW242 requests
Withdrawn4,524860.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J844, Knox County
Onshore wind
300 MWUnder construction Knox, ILMISO Jun 2017target 2021
Onshore wind project J1781, Iowa County
Onshore wind
300 MWUnder construction Iowa, WIMISO Jun 2020target 2027
Onshore wind project J848, Christian County
Onshore wind
250 MWUnder construction Christian, ILMISO Jun 2017target 2021
Onshore wind project J1040, Mcintosh County
Onshore wind
250 MWUnder construction Mcintosh, NDMISO Mar 2018target 2023
Onshore wind project J1069, Jasper County
Onshore wind
200 MWUnder construction Jasper, INMISO Mar 2018target 2023
Onshore wind project J1115, Macon County
Onshore wind
200 MWUnder construction Macon, ILMISO Mar 2018target 2024
Onshore wind project J722, Codington County
Onshore wind
200 MWUnder construction Codington, SDMISO Jun 2017target 2023
Onshore wind project J984, Gratiot County
Onshore wind
200 MWUnder construction Gratiot, MIMISO Mar 20182023
Onshore wind project J866, Tunica County
Onshore wind
200 MWUnder construction Tunica, MSMISO Jun 20172024
Onshore wind project J1437, Carroll County
Onshore wind
180 MWUnder construction Carroll, ARMISO Apr 2019target 2024
Onshore wind project J967, Mower County
Onshore wind
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Onshore wind project J750, Morgan County
Onshore wind
150 MWUnder construction Morgan, ILMISO Jun 2017target 2022
Onshore wind project J855, Grant County
Onshore wind
100 MWUnder construction Grant, WIMISO Jun 20172023
Onshore wind project J898, Howard County
Onshore wind
100 MWUnder construction Howard, IAMISO Jun 2017target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)