United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Wisconsin

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2212.4 GW
Active in queue12.4 GW22 requests
Agreement signed21.0 MW1 requests
Withdrawn2713.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

22 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Red Oak Ridge Energy Center
Gas Β· Invenergy
1,211 MWIn study Kenosha, WIMISO Aug 2025target 2027
Gas project E0016, Calumet County
Gas Β· Invenergy
1,211 MWIn study Calumet, WIMISO Aug 2025target 2027
Gas project J4164, Dane County
Gas
1,203 MWIn study Dane, WIMISO Sep 2025target 2030
Gas project J4165, Kenosha County
Gas
1,203 MWIn study Kenosha, WIMISO Sep 2025target 2030
Gas project J4014, Calumet County
Gas
1,203 MWIn study Calumet, WIMISO May 2025target 2030
Replacement; Oak Creek Units 5-8
Gas
1,138 MWIn study Milwaukee, WIMISO Jun 2024target 2027
Gas project J4116, Walworth County
Gas
950 MWIn study Walworth, WIMISO Oct 2025target 2030
Gas project J732, Douglas County
Gas
562 MWUnder construction Douglas, WIMISO Jun 2017target 2023
Gas project J4115, Fond Du Lac County
Gas
525 MWIn study Fond Du Lac, WIMISO Oct 2025target 2028
Gas project J4144, Columbia County
Gas
525 MWIn study Columbia, WIMISO Oct 2025target 2030
Gas project E0037, Sheboygan County
Gas Β· Wisconsin Power and Light Company (WPL)
455 MWIn study Sheboygan, WIMISO Aug 2025target 2025
Gas project E0038, Winnebago County
Gas Β· Wisconsin Power and Light Company (WPL)
455 MWIn study Winnebago, WIMISO Aug 2025target 2025
Gas project J2944, Portage County
Gas
350 MWIn study Portage, WIMISO Sep 2022target 2027
Gas project J4028, Walworth County
Gas
324 MWIn study Walworth, WIMISO May 2025target 2027
Gas project J2947, Rock County
Gas
205 MWIn study Rock, WIMISO Sep 2022target 2026
Gas project J3152, Green County
Gas
160 MWIn study Green, WIMISO Sep 2022target 2027
Gas project J3155, Winnebago County
Gas
150 MWIn study Winnebago, WIMISO Sep 2022target 2025
Gas project J3151, Sheboygan County
Gas
150 MWIn study Sheboygan, WIMISO Sep 2022target 2025
Gas project J3936, Kenosha County
Gas
132 MWIn study Kenosha, WIMISO Feb 2025target 2027
Surplus; J1316
Gas
132 MWIn study Kenosha, WIMISO Jan 2025target 2026
Gas project J3156, Rock County
Gas
100 MWIn study Rock, WIMISO Sep 2022target 2026
Gas project J384, Dane County
Gas
21.0 MWAgreement signed Dane, WIMISO Aug 2014target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)